United States βΊ Grid βΊ Interconnection queues βΊ Minnesota
ONSHORE WIND Β· MISOOnshore wind project J3125, Cottonwood County
Onshore wind project J3125, Cottonwood County is a 289 MW onshore wind request withdrawn in the MISO interconnection queue, in Cottonwood County, Minnesota, connecting to NORTHERN STATES POWER COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2022 (completed)
- Withdrawn / abandonedOct 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J3125
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- NORTHERN STATES POWER COMPANY
- Connection point (POI)
- Crandall 345 kV Substation
- Location
- Cottonwood County, Minnesota
- Technology
- Wind: 289 MW
- Total requested
- 289 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 14 September 2022
- Proposed online date
- June 2027
- Withdrawn
- October 2025
Location
Marker shows the centre of Cottonwood County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Cottonwood County
- Surplus; Big BendWind + storage Β· 550 MW Β· in study
- Onshore wind project J2332, Cottonwood CountyOnshore wind Β· 200 MW Β· in study
- Onshore wind project J2563, Cottonwood CountyOnshore wind Β· 200 MW Β· in study
- Onshore wind project G442, Cottonwood CountyOnshore wind Β· 50.0 MW Β· built
- Onshore wind project G375, Cottonwood CountyOnshore wind Β· 20.0 MW Β· built
- Onshore wind project G532, Cottonwood CountyOnshore wind Β· 20.0 MW Β· built
- Gas project G341, Cottonwood CountyGas Β· 2.0 MW Β· built
- Onshore wind project J1315, Cottonwood CountyOnshore wind Β· 600 MW Β· withdrawn
- Other project J1349, Cottonwood CountyOther Β· 335 MW Β· withdrawn
- Onshore wind project J742, Cottonwood CountyOnshore wind Β· 211 MW Β· withdrawn
- Onshore wind project J726, Cottonwood CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project J965, Cottonwood CountyOnshore wind Β· 150 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem