United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESQueue requests in study in PJM (Mid-Atlantic, Midwest) — page 10
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project AH2-195, Indiana County Solar |
65.0 MW | In study |
| Solar project AH1-546, Buckingham County Solar · Mountain Pine Arvonia LLC |
65.0 MW | In study |
| Solar + storage project AI1-079, Adair County Solar + storage |
64.8 MW | In study |
| Solar project AI1-147, Dekalb County Solar |
64.0 MW | In study |
| Morrow County Solar II Solar |
64.0 MW | Paused / redesign |
| Solar + storage project AG2-424, Larue County Solar + storage · Magnolia Solar and Grazing Farm LLC |
63.3 MW | In study |
| Solar project AG2-411, Somerset County Solar · Iris Energy LLC |
63.0 MW | In study |
| Battery storage project AH2-072, Washington County Battery storage |
62.1 MW | In study |
| Cerulean Solar and Mulberry BESS Solar · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) |
62.0 MW | In study |
| Battery storage project AG2-384, Chesterfield County Battery storage · Virginia Electric and Power Company |
60.8 MW | In study |
| Battery storage project AI2-307, Cecil County Battery storage |
60.5 MW | In study |
| Moon Corner Solar Solar · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) |
60.0 MW | In study |
| Solar project AG2-171, Lunenburg County Solar · Couch Creek Solar LLC |
60.0 MW | In study |
| Solar project AI1-105, Luzerne County Solar |
60.0 MW | In study |
| Battery storage project AH2-032, Prince William County Battery storage |
60.0 MW | In study |
| Sweetleaf Solar Solar |
60.0 MW | Paused / redesign |
| Chestnut Solar Solar |
60.0 MW | Paused / redesign |
| Gas project AI2-022, Bradford County Gas |
60.0 MW | In study |
| Battery storage project AH2-033, Prince William County Battery storage |
60.0 MW | In study |
| Battery storage project AI2-231A, Botetourt County Battery storage |
60.0 MW | In study |
| Solar project AI2-024, Meigs County Solar |
60.0 MW | In study |
| Lafayette Storage Battery storage · Lafayette Energy, LLC |
60.0 MW | In study |
| Solar + storage project AI2-444 Solar + storage |
59.5 MW | In study |
| Solar project AI1-123, Lunenburg County Solar |
59.0 MW | In study |
| Solar project AI2-245, Woodford County Solar |
55.2 MW | In study |
| Dover Solar Facility Solar |
55.0 MW | Paused / redesign |
| Battery storage project AG2-272, Pittsylvania County Battery storage · Tupelo Storage, LLC |
55.0 MW | In study |
| Hardin Energy Center – Storage II Battery storage |
55.0 MW | Paused / redesign |
| Solar project AG2-617, Anne Arundel County Solar · Dairy Farm Solar, L.L.C. |
55.0 MW | In study |
| Bluestem Solar Battery storage · RWE Solar Development, LLC |
55.0 MW | In study |
| Solar project AI2-224, Charlotte County Solar |
55.0 MW | In study |
| Battery storage project AH2-061, Prince William County Battery storage |
55.0 MW | In study |
| Solar project AG2-585, Kankakee County Solar · Grand Marsh Solar 2, LLC |
55.0 MW | In study |
| Dover Solar Solar |
55.0 MW | Paused / redesign |
| Battery storage project AH2-060, Prince William County Battery storage |
55.0 MW | In study |
| Gas project AH1-744, Prince George's County Gas · Parkway Generation Operating LLC |
53.5 MW | In study |
| Solar project AI1-151, Adams County Solar |
53.2 MW | In study |
| Solar project AG2-073, Madison County Solar · SR Madison, LLC |
53.0 MW | In study |
| Solar project AH2-080, Brunswick County Solar |
52.7 MW | In study |
| Solar + storage project AH2-076, Perry County Solar + storage |
52.5 MW | In study |
| Battery storage project AH2-145, King George County Battery storage |
52.3 MW | In study |
| Clermont County Solar Project Battery storage |
52.2 MW | Paused / redesign |
| Battery storage project AH2-372, Stephenson County Battery storage |
52.0 MW | In study |
| Gas project AG2-562, St. Joseph County Gas · St. Joseph Energy Center, LLC |
52.0 MW | In study |
| Solar + storage project AH2-199, Will County Solar + storage |
51.7 MW | In study |
| Solar project AI1-120, Warren County Solar |
51.6 MW | In study |
| Solar project AI2-196, Lycoming County Solar |
51.5 MW | In study |
| Solar project AH1-227, Wise County Solar · Virginia Electric and Power Company |
51.3 MW | In study |
| Gas project AH1-703, Bergen County Gas · Parkway Generation Operating LLC |
51.3 MW | In study |
| Solar project AI2-244, Nottoway County Solar |
50.3 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)1,496 · 455.6 GW
- ERCOT (Texas)1,408 · 328.0 GW
- MISO (Midcontinent)1,337 · 302.2 GW
- Southeast (non-ISO utilities)815 · 118.5 GW
- SPP (Southwest Power Pool)480 · 114.8 GW
- PJM (Mid-Atlantic, Midwest)905 · 105.4 GW
- CAISO (California)194 · 92.4 GW
- NYISO (New York)190 · 27.1 GW
- ISO-NE (New England)27 · 6,015 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)