Battery storage projects in the connection queue on the National Grid (England & Wales) network

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown503151.0 GW in total
In planning360scoping or awaiting consent
Consented or building77closest to connecting
Built66connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

503 projects · page 7 of 11
ProjectCapacityStageConnection siteFrom
Yaxley BESS
Battery storage · Field Yaxley Ltd
200 MWScoping North Anglia Connection Node E 400kV Substation
National Grid (England & Wales)
Oct 2034
Tyler Hill Iver
Battery storage · FRV Powertek Limited
200 MWAwaiting Consents London West Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2038
Manor Farm_Sidcup
Battery storage · Firstway Solar Ltd
200 MWScoping North Kent Connection Node C 132Kv Substation
National Grid (England & Wales)
Oct 2037
Mill Hey_Capenhurst BESS
Battery storage · Firstway Solar Ltd
200 MWScoping Capenhurst GSP
National Grid (England & Wales)
Oct 2037
Deeside Power Station
Battery storage · Deeside Power (UK) Limited
190 MWBuilt Connah's Quay 400kV Substation
National Grid (England & Wales)
Oct 2026
NEL Nicholson
Battery storage · UE 2 LTD
180 MWScoping Thorpe Marsh GSP
National Grid (England & Wales)
Oct 2035
Elstree Energy Storage
Battery storage · Elstree Battery Storage Limited
170 MWScoping Letchmore Heath 132kV Substation
National Grid (England & Wales)
Jul 2030
Vicarage Drove BESS Limited
Battery storage · Vicarage Drove BESS Limited
160 MWScoping Navenby 132kV Substation
National Grid (England & Wales)
Oct 2039
Moelfre Energy Park
Battery storage · Moelfre Energy Park Limited
158 MWScoping Bodelwyddan 400kV Substation
National Grid (England & Wales)
Oct 2029
Axminster BESS
Battery storage · Cse25 Limited
150 MWScoping Axminster 132kV Substation
National Grid (England & Wales)
Oct 2028
BESS North Farm
Battery storage · Rewe 5 Limited
150 MWScoping Chickerell 400kV Substation
National Grid (England & Wales)
Nov 2031
Clifton Lane 150MW BSS
Battery storage · Renewables North West Ltd
150 MWScoping Frodsham 132kV
National Grid (England & Wales)
Oct 2037
Copper Nose BESS
Battery storage · Copper Nose Energy Ltd
150 MWScoping Fawley 132kV Substation
National Grid (England & Wales)
Oct 2036
Ebstree Road BESS
Battery storage · Voltwise Power Holdings Limited
150 MWScoping Staffordshire Connection Node B 132kV Substation
National Grid (England & Wales)
Oct 2037
Fairgreen Energy Storage
Battery storage · Renewable Energy Systems Limited
150 MWScoping Rayleigh Main 132kV Substation
National Grid (England & Wales)
Oct 2034
Feckenham Greener Grid Park
Battery storage · Statkraft UK Ltd
150 MWScoping Feckenham 400kV Substation
National Grid (England & Wales)
Oct 2032
Norrington Gate
Battery storage · Adv 004 Limited
150 MWConsents Approved Melksham B 132KV Substation
National Grid (England & Wales)
Sep 2037
Prestwold BESS
Battery storage · Greentech Projects Holding UK Limited
150 MWScoping Derbyshire Connection Node F 132KV
National Grid (England & Wales)
Oct 2037
SSE Ferrybridge BESS
Battery storage · Sse Battery Salisbury Limited
150 MWBuilt Ferrybridge B 132kV Substation
National Grid (England & Wales)
SSE Fiddlers Ferry Battery Energy Storage
Battery storage · Littleton Pastures Solar Limited
150 MWConsents Approved Fiddlers Ferry 275kV Substation
National Grid (England & Wales)
Feb 2027
Sutton Courtenay
Battery storage · RWE Generation UK Plc
150 MWScoping Didcot 132kV Substation
National Grid (England & Wales)
Oct 2037
Water Orton
Battery storage · Voltwise Power Holdings Limited
150 MWScoping Warwickshire Connection Node F 132kV Substation
National Grid (England & Wales)
Oct 2037
Weaver Island 150MW BESS
Battery storage · Weaver Island BESS Ltd
150 MWScoping Elton (Merseyside 132kV Substation)
National Grid (England & Wales)
Oct 2037
Whitson BESS
Battery storage · Field Devco Ltd
150 MWScoping Whitson 275kV Substation
National Grid (England & Wales)
Oct 2037
Wilton Lion BESS
Battery storage · Sembcorp (Wilton BESS) Limited
150 MWBuilt Greystones A 275kV Substation
National Grid (England & Wales)
Witney BESS
Battery storage · Voltwise Power Holdings Limited
150 MWScoping Cowley GSP
National Grid (England & Wales)
Nov 2038
Zenobe Norton
Battery storage · Zenobe Energy Limited
150 MWAwaiting Consents Norton East 400kV Substation
National Grid (England & Wales)
Oct 2031
Zenobe Stalybridge Project
Battery storage · Zenobe Stalybridge Limited
150 MWScoping Stalybridge 275kV Substation
National Grid (England & Wales)
Sep 2027
Sizing John (Rainhill)
Battery storage · Sizing John Limited
143 MWConsents Approved Rainhill GSP
National Grid (England & Wales)
Sep 2026
Severn Road Avonmouth
Battery storage · Fpc Electric Land Limited
135 MWScoping Seabank GSP
National Grid (England & Wales)
Oct 2038
Vox Charlie
Battery storage · Vox Charlie Ltd
125 MWScoping Amersham Main 132kV Substation
National Grid (England & Wales)
Oct 2037
Axminster
Battery storage · HB825AXM LTD
120 MWAwaiting Consents Axminster 132kV Substation
National Grid (England & Wales)
Oct 2024
Axminster - New Connection
Battery storage · Enso Green Holdings B Limited
120 MWScoping Axminster 132kV Substation
National Grid (England & Wales)
Jun 2029
Brentford (SSEN-FBT624) -120MW BESS
Battery storage · Lightsource Renewable UK Development Limited
120 MWScoping West London Connection Node B 132kV substation
National Grid (England & Wales)
Oct 2038
Drakelow
Battery storage · Enso Green Holdings V Limited
120 MWScoping Drakelow 132kV Substation
National Grid (England & Wales)
Dec 2027
Iron Acton
Battery storage · HD000ACT LTD
120 MWConsents Approved Iron Acton 275kV Substation
National Grid (England & Wales)
Oct 2028
Lincomb Farm 120MW BESS Scheme
Battery storage · Fpc Electric Land Limited
120 MWScoping Bishops Wood 132kV Substation
National Grid (England & Wales)
Jun 2033
Pembroke (spare bay)
Battery storage · Pembroke Green Limited
120 MWConsents Approved Pembroke 132kV Substation
National Grid (England & Wales)
Jul 2028
Pigeon House BESS
Battery storage · Voltwise Power Holdings Limited
120 MWScoping Solent Connection Node B 132kV Substation
National Grid (England & Wales)
Oct 2037
Ratcliffe on Soar BESS
Battery storage · Fpc Electric Land Limited
120 MWScoping Kegworth B (Derbyshire Connection Node C) 132kV Substation
National Grid (England & Wales)
Oct 2037
Uskmouth - New Connection
Battery storage · Aw1 Energy Storage Limited
120 MWUnder Construction/Commissioning Uskmouth 132kV Substation
National Grid (England & Wales)
Oct 2026
Barry Road Storage
Battery storage · Bsr Applications Limited
110 MWScoping Severn Connection Node A 132kV Substation
National Grid (England & Wales)
Oct 2037
Old Stoke Rd BESS
Battery storage · Cubico UK Development Limited
105 MWScoping North Anglia Connection Node A 132kV Substation
National Grid (England & Wales)
Oct 2034
Alverdiscott
Battery storage · Pivoted Power LLP
100 MWScoping Alverdiscott 400kV Substation
National Grid (England & Wales)
Oct 2036
Bradford West 100MW
Battery storage · Old Allen Road BESS Limited
100 MWConsents Approved Bradford West 275kV Substation
National Grid (England & Wales)
May 2027
Capenhurst 275KV Substation
Battery storage · Zenobe Capenhurst Limited
100 MWBuilt Capenhurst 275kV Substation
National Grid (England & Wales)
Didcot Battery
Battery storage · Didcot Battery Limited
100 MWScoping Didcot 400/132Kv Substation
National Grid (England & Wales)
Mar 2027
Feckenham 100MW BESS
Battery storage · Energycog Ltd
100 MWScoping Warwickshire Connection Node B 132kV Substation
National Grid (England & Wales)
Oct 2037
Fryston Lane 100MW BESS
Battery storage · GPC 2008 Ltd
100 MWScoping Leeds North Connection Node C 132kV Substation
National Grid (England & Wales)
Oct 2035
Larks Green Farm BESS
Battery storage · Voltalia UK Ltd
100 MWScoping Iron Acton 132kV Substation
National Grid (England & Wales)
Oct 2037
Page 7 of 11

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.