NESO TEC REGISTER · GREAT BRITAIN

Grid connection projects in the connection queue on the SSEN Transmission (north Scotland) network

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown30385.5 GW in total
In planning303scoping or awaiting consent
Consented or building52closest to connecting
Built89connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

303 projects · page 3 of 7
ProjectCapacityStageConnection siteFrom
Myreton BESS
Battery storage · GPC 1039 Ltd
200 MWScoping Tealing 132kV Substation
SSEN Transmission (north Scotland)
Oct 2028
Netherton Hub Bess
Battery storage · Field Netherton Ltd
200 MWScoping Longside 400kV Substation
SSEN Transmission (north Scotland)
Oct 2033
New Deer 2 BESS
Battery storage · Field New Deer Ltd
200 MWScoping New Deer 2 400kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Rigifa BESS
Battery storage · Field Rigifa Limited
200 MWScoping Gills Bay 132kV
SSEN Transmission (north Scotland)
Dec 2029
Salamander Offshore Wind Farm
Offshore wind · Salamander Wind Project Company Limited
200 MWScoping Peterhead 132KV Substation
SSEN Transmission (north Scotland)
Mar 2030
Tolkien Solar Farm
Solar + storage · Tolkien Solar Farm Limited
200 MWScoping Tolkien Farm 132kV Substation
SSEN Transmission (north Scotland)
Oct 2033
West Saval Battery Storage
Battery storage · West Saval Battery Storage Ltd
200 MWScoping West Saval Substation 132 kV
SSEN Transmission (north Scotland)
Oct 2030
Womblehill BESS Farm
Battery storage · RE Projects Development Limited
200 MWScoping Womblehill BESS Farm 132kV
SSEN Transmission (north Scotland)
Dec 2029
Zenobe New Deer Battery Storage
Battery storage · Zenobe Energy Limited
200 MWScoping New Deer 400kV Substation
SSEN Transmission (north Scotland)
Oct 2029
Inveroykel Wind Farm
Onshore wind · Rwe Renewables UK Swindon Limited
191 MWScoping Inveroykel Wind Farm 132kV
SSEN Transmission (north Scotland)
Oct 2031
Clune Wind Farm
Wind + storage · Renewable Energy Systems Limited
187 MWScoping Clune 132/33 kV Substation
SSEN Transmission (north Scotland)
Apr 2030
Upper Greenfields BESS
Battery storage · S4 UK DEV LTD
175 MWScoping New Deer 2 132kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Creag Dhubh Windfarm
Wind + storage · Invenergy Development UK Ltd
171 MWScoping Creag Dhubh Wind Farm and BESS 132kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Limekiln Extension 2
Wind + storage · Boralex Limited
171 MWScoping New Limekiln 132 kV Substation
SSEN Transmission (north Scotland)
Oct 2037
Elchies Wind Farm
Onshore wind · Elchies Wind Limited
170 MWScoping Elchies 132/33kV Substation
SSEN Transmission (north Scotland)
Nov 2028
Gresham House Connagill BESS
Battery storage · Energyhubdevelopments Limited
170 MWScoping New Connagill 275/132kV Substation
SSEN Transmission (north Scotland)
Oct 2031
Scotsburn Road
Battery storage · Tbc 002 Limited
170 MWScoping Fyrish 275kV Substation
SSEN Transmission (north Scotland)
Oct 2030
Highland Wind Farm
Wind + storage · Highland Wind Farm Limited
168 MWScoping Highland Wind Farm 132/33kV substation
SSEN Transmission (north Scotland)
Oct 2030
Limekiln
Wind + storage · Limekiln Extension Limited
167 MWScoping Limekilns 132/33kV substation
SSEN Transmission (north Scotland)
Dec 2030
Glendye Wind Farm
Onshore wind · Glendye Wind Farm Limited
167 MWScoping Glendye Wind Farm Substation
SSEN Transmission (north Scotland)
Apr 2034
Deucheran Hill 2 Wind Farm
Wind + storage · RWE Renewables UK Onshore Wind Limited
165 MWScoping Deucheran Hill 2 132Kv Substation
SSEN Transmission (north Scotland)
Oct 2034
Glen Lednock
Wind + storage · Glen Lednock Wind Farm Limited
165 MWScoping Glen Lednock 132kV Substation
SSEN Transmission (north Scotland)
Nov 2031
Balvedavist 162 Battery Storage
Solar + storage · S4N Spittal Ltd
162 MWAwaiting Consents Spittal 132kV Substation
SSEN Transmission (north Scotland)
Oct 2030
Balinoe Wind Farm
Wind + storage · RWE Renewables UK Onshore Wind Limited
161 MWScoping Balinoe 132kV substation
SSEN Transmission (north Scotland)
Oct 2034
Tioram Wind Farm
Onshore wind · Invenergy Development UK Ltd
160 MWScoping New Carradale 132Kv Substation
SSEN Transmission (north Scotland)
Oct 2037
Ruith Cnoc
Onshore wind · Ruith Cnoc Wind Farm Limited
158 MWScoping New Dalchork 132kV Substation
SSEN Transmission (north Scotland)
Oct 2037
Galileo 12 Limited
Solar + storage · Galileo 12 Limited
151 MWScoping Fetteresso 132kV substation
SSEN Transmission (north Scotland)
Oct 2033
Meall Dearg
Wind + storage · Energyfarm UK Meall Dearg Ltd
150 MWScoping New North West 132kV Substation
SSEN Transmission (north Scotland)
Oct 2037
Balrobert Farm BESS
Battery storage · Elgin Energy Es Co Limited
150 MWScoping Knocknagael 132kV Substation
SSEN Transmission (north Scotland)
Oct 2032
Cnoc Buidhe Wind Farm
Wind + storage · Cnoc Buidhe Wind Energy Hub Limited
150 MWScoping Cnoc Buidhe 132kV/33kV Substation
SSEN Transmission (north Scotland)
Apr 2030
Drum of Clunas Wind and Solar Park
Onshore wind · Broadhaven Distribution Limited
150 MWScoping Drum Of Clunas Wind 275Kv Substation
SSEN Transmission (north Scotland)
Oct 2031
Galileo 07 Limited
Solar + storage · Galileo 07 Limited
150 MWScoping Galileo 07 Limited 132Kv Substation
SSEN Transmission (north Scotland)
Oct 2032
Kedrum Solar Farm
Solar + storage · Rosside Energy Limited
150 MWAwaiting Consents Blackhillock 275kV Substation
SSEN Transmission (north Scotland)
May 2030
Keith Solar Farm
Solar + storage · Keith Solar Pv Limited
150 MWScoping Keith Solar Farm 275kV Substation
SSEN Transmission (north Scotland)
Oct 2028
Achrugan Wind Farm
Wind + storage · Statkraft Windco 1 Limited
149 MWScoping Achrugan 132kV Substation
SSEN Transmission (north Scotland)
Jul 2030
Ballach
Wind + storage · Energyfarm UK Ballach Ltd
149 MWScoping New North West 132kV Substation
SSEN Transmission (north Scotland)
Oct 2037
Clashindarroch Windfarm Extension
Onshore wind · Clashindarroch Windfarm Extension Limited
145 MWScoping Clashindarroch Windfarm Extension 132kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Farr WindFarm
Onshore wind · Farr Windfarm Limited
145 MWScoping Farr Wind Farm 132/33Kv Substation
SSEN Transmission (north Scotland)
Jan 2030
Beinneun 2 Windfarm
Onshore wind · Beinneun 2 Limited
144 MWScoping Beinneun Windfarm 2
SSEN Transmission (north Scotland)
Oct 2037
Aberarder Extension Wind Farm
Wind + storage · Renewable Energy Systems Limited
138 MWScoping Aberarder Extension Wind Farm 132/33kV Substation
SSEN Transmission (north Scotland)
Apr 2031
Knockton Wind Farm
Onshore wind · Perigus Energy UK Limited
130 MWScoping Alyth 400kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Altnabreac Windfarm
Wind + storage · Altnabreac Wind Farm Limited
130 MWScoping Connagill 275kV Substation
SSEN Transmission (north Scotland)
Oct 2032
Glendye Wind Farm
Onshore wind · Glendye Wind Farm Limited
125 MWScoping Glendye Wind Farm Substation
SSEN Transmission (north Scotland)
Oct 2028
Highland BESS
Battery storage · Apatura Battery Ltd
120 MWScoping Highland BESS 132kV Substation
SSEN Transmission (north Scotland)
May 2030
Culachy Wind Farm
Wind + storage · Fred Olsen Renewables Limited
115 MWScoping Fort Augustus 2 400kV Substation
SSEN Transmission (north Scotland)
Oct 2037
Lethen Wind Farm
Onshore wind · Fred Olsen Renewables Limited
114 MWScoping Lethen Wind Farm 132/33kV Substation
SSEN Transmission (north Scotland)
Dec 2033
Coille Linne
Wind + storage · Energyfarm UK Coille Linne Ltd
113 MWScoping Coille Linne 132kV Substation
SSEN Transmission (north Scotland)
Oct 2037
Teindland Wind Farm
Onshore wind · Teindland Wind Farm Limited
112 MWAwaiting Consents Blackhillock substation
SSEN Transmission (north Scotland)
Sep 2029
Colmealie Wind - Solar - BESS Farm
Solar + storage · Galileo 21 Limited
112 MWScoping New Fetteresso 132Kv Substation
SSEN Transmission (north Scotland)
Oct 2037
Achany Extension Wind Farm
Onshore wind · Sse Generation Limited
105 MWAwaiting Consents ACHANY EXTENSION WIND FARM 132/33KV Substation
SSEN Transmission (north Scotland)
Mar 2028

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.