Grid infrastructure βΊ Connection queue βΊ Wind + storage
WIND + STORAGE Β· SHETCoille Linne
Coille Linne is a 113 MW wind + storage project in planning, connecting to the SSEN Transmission (north Scotland) network at Coille Linne 132kV Substation, with capacity due from October 2037. The connection agreement is held by Energyfarm UK Coille Linne Ltd.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2037 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-005983
- Customer
- Energyfarm UK Coille Linne Ltd
- Technology
- Energy Storage System, Wind Onshore
- Total capacity
- 113 MW
- Change in this agreement
- +113 MW
- Capacity effective from
- 31 October 2037
- Connection site
- Coille Linne 132kV Substation
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
Connection site
The connection site could not be placed on the map.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem