Farr WindFarm

Farr WindFarm is a 145 MW onshore wind project in planning, connecting to the SSEN Transmission (north Scotland) network at Farr Wind Farm 132/33Kv Substation, with capacity due from January 2030. The connection agreement is held by Farr Windfarm Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Jan 2030 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-004381
Customer
Farr Windfarm Limited
Technology
Wind Onshore
Total capacity
145 MW
Change in this agreement
+145 MW
Capacity effective from
30 January 2030
Connection site
Farr Wind Farm 132/33Kv Substation
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The connection site could not be placed on the map.

Projects connecting near Farr Wind Farm · Grid map