Home › Grid infrastructure › Connection queue

NESO TEC REGISTER · GREAT BRITAIN

Solar + storage projects in the connection queue

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown569220.5 GW in total
In planning513scoping or awaiting consent
Consented or building47closest to connecting
Built9connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

569 projects · page 2 of 12
ProjectCapacityStageConnection siteFrom
Rye House
Solar + storage · Rye House 10 Renewables Limited
1.0 GWScoping London North East Connection Node A
National Grid (England & Wales)
Oct 2031
Sellindge West
Solar + storage · Sellindge West 10 Renewables Limited
1.0 GWScoping East Kent connection node A 400kV Substation
National Grid (England & Wales)
Oct 2033
Spalding High Impact Energy Hub
Solar + storage · Telis Energy UK Limited
1.0 GWScoping West Anglia Connection Node G 400kV Substation
National Grid (England & Wales)
Oct 2034
Stoke Bardolph
Solar + storage · Stoke Bardolph 10 Renewables Limited
1.0 GWScoping Trent Valley South Connection Node D 400kV Substation
National Grid (England & Wales)
Oct 2034
West Weybridge
Solar + storage · West Weybridge 10 Renewables Limited
1.0 GWScoping London North West Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2038
Wymondley Farm
Solar + storage · Wymondley 10 Renewables Ltd
1.0 GWScoping West Anglia Connection Node B 400Kv Substation
National Grid (England & Wales)
Oct 2032
Wymondley High Impact Green Energy Hub (HIGEH) 1
Solar + storage · Telis Energy UK Limited
1.0 GWScoping Wymondley 400kV Substation
National Grid (England & Wales)
Oct 2033
Norwich Main BESS
Solar + storage · Tasway Energy Park Limited
950 MWScoping North Anglia Connection Node A 400kV
National Grid (England & Wales)
Oct 2034
Thornton Facility
Solar + storage · Balwen Limited
930 MWConsents Approved Thornton 400kV Substation
National Grid (England & Wales)
Oct 2032
Alyth
Solar + storage · Ecodev (Alyth) Ltd
900 MWScoping Alyth Solar and Battery 400/132kV
SSEN Transmission (north Scotland)
Oct 2033
Elmya Gissing BESS & PV
Solar + storage · Rpc Elmya Carnation Gissing Limited
900 MWScoping North Anglia Connection Node A 400kV
National Grid (England & Wales)
Oct 2034
Norfolk001
Solar + storage · Epl Newco1 Limited
860 MWScoping Walpole 400kV Substation
National Grid (England & Wales)
Nov 2031
Bradenham - Thetford (Necton) GEC (Ethos Green)
Solar + storage · Necton Green Energy Centre Ltd
850 MWScoping Necton 400kV Substation
National Grid (England & Wales)
Oct 2033
Buntington GEC
Solar + storage · Buntington Green Energy Centre Ltd
850 MWAwaiting Consents Cottered 400kV Substation
National Grid (England & Wales)
Jul 2032
Elmya Kilworth BESS & PV
Solar + storage · Rpc Elmya Carnation Kilworth Limited
850 MWScoping Derbyshire Connection Node H 400kV Substation
National Grid (England & Wales)
Oct 2037
Elmya Ryston BESS & PV
Solar + storage · Elmya Energy UK 13 Limited
850 MWScoping North Anglia Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2034
Hockliffe GEC (Ethos Green)
Solar + storage · Hockliffe Green Energy Centre Ltd
850 MWScoping Dunstable 400kV Substation
National Grid (England & Wales)
Oct 2032
Grantham Solar Farm - RSL
Solar + storage · South Grantham Energy Centre Limited
810 MWScoping Trent Valley South Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2034
Botley GEC (Ethos Green)
Solar + storage · Botley Green Energy Centre Ltd
800 MWAwaiting Consents Botley 400kV Substation
National Grid (England & Wales)
Oct 2033
Cliff Hill Energy Farm
Solar + storage · Renewable Energy Systems Limited
800 MWScoping Navenby 400kV Substation
National Grid (England & Wales)
Oct 2034
East Lincolnshire Solar
Solar + storage · Statkraft UK Ltd
800 MWScoping Lincolnshire Coastal Node B 400kV Substation
National Grid (England & Wales)
May 2035
Flash Solar Farm
Solar + storage · Elements Green Trent Ltd
800 MWConsents Approved Staythorpe 400kV Substation
National Grid (England & Wales)
May 2028
Hill Street Solar PV/BESS Station
Solar + storage · Hill Street Shelfco 1 Limited
800 MWScoping Staffordshire Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
Melksham BESS & PV
Solar + storage · Elements Green Limited
800 MWScoping Melksham 400kV Substation
National Grid (England & Wales)
Oct 2037
Monk Fryston Energy Park
Solar + storage · Elements Green Development Ltd
800 MWScoping Monk Fryston 400kV Substation
National Grid (England & Wales)
Oct 2035
Scarning
Solar + storage · Connectid 3 Limited
800 MWAwaiting Consents North Anglia Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2034
Springwell
Solar + storage · Springwell Energyfarm Limited
800 MWScoping Navenby 400kV Substation
National Grid (England & Wales)
Oct 2030
Stockhills Farm
Solar + storage · Bsr Applications Limited
800 MWScoping Severn Connection Node A 400kv Substation
National Grid (England & Wales)
Oct 2037
Sweet Briar Energy Park
Solar + storage · Sweet Briar 2 Energy Park Limited
800 MWScoping South Humber Connection Node A
National Grid (England & Wales)
Oct 2035
Tween Bridge Solar Park
Solar + storage · RWE Renewables UK Solar and Storage Limited
800 MWScoping Trent Valley North Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2037
New Marton Solar Farm - PVDP
Solar + storage · SolarFour Ltd
780 MWScoping Cheshire Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
East Pit
Solar + storage · Cs UK Holdings III Limited
750 MWScoping Rhigos 400kV Substation
National Grid (England & Wales)
Oct 2037
Meridian Solar Farm
Solar + storage · Meridian Solar Farm Limited
750 MWScoping Weston Marsh 400kV Substation
National Grid (England & Wales)
Jun 2033
Old Flatts Farm
Solar + storage · Net Zero One Ltd
750 MWScoping Brinsworth 400kV Substation
National Grid (England & Wales)
Oct 2029
Wyseby Hill Energy Farm
Solar + storage · Wysebyhill Energy Farm Limited
750 MWScoping Wyseby Hill Energy Farm 400kV Substation
SP Transmission (south Scotland)
Oct 2031
One Earth Solar Farm
Solar + storage · One Earth Solar Farm Limited
740 MWAwaiting Consents High Marnham 400kV Substation
National Grid (England & Wales)
Oct 2029
J212 High Grove Solar
Solar + storage · RWE Renewables UK Solar and Storage Limited
720 MWAwaiting Consents Thetford 400kV Substation
National Grid (England & Wales)
Oct 2031
Welbeck-Newark Solar Farm - PVDP
Solar + storage · SolarTen Ltd
710 MWScoping High Marnham 400kV Substation
National Grid (England & Wales)
Oct 2034
Bolney Farm 2
Solar + storage · Dragon Green 7 Renewables Ltd
700 MWScoping DRAGON GREEN 400kV SUBSTATION
National Grid (England & Wales)
Nov 2037
Bramley Farm 2
Solar + storage · Bramley 7 Renewables Ltd
700 MWScoping Basingstoke East 400kV Substation
National Grid (England & Wales)
May 2038
Cowley Farm 2
Solar + storage · Cowley 7 Renewables Ltd
700 MWScoping Cowley 400kV Substation
National Grid (England & Wales)
Nov 2038
Didcot Farm 2
Solar + storage · Appleford 7 Renewables Limited
700 MWScoping APPLEFORD 400kV SUBSTATION
National Grid (England & Wales)
Oct 2037
Enderby Farm 2
Solar + storage · 548 UK Investment Holdings Limited
700 MWScoping Earl Shilton 400kV Substation
National Grid (England & Wales)
Oct 2034
Fleet Farm 2
Solar + storage · Basingstoke East 7 Renewables Ltd
700 MWScoping Basingstoke East 400kV Substation
National Grid (England & Wales)
Jun 2038
Grantham Generation
Solar + storage · Aukera Energy Limited
700 MWScoping Trent Valley South Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2035
Great Oak Solar
Solar + storage · RWE Renewables UK Solar and Storage Limited
700 MWScoping South Anglia Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2034
Market Harborough
Solar + storage · Connectid 1 Limited
700 MWAwaiting Consents West Anglia Connection Node F 400kV Substation
National Grid (England & Wales)
Oct 2034
Pelham Farm 2
Solar + storage · 548 UK Investment Holdings Limited
700 MWScoping Pelham 400kV Substation
National Grid (England & Wales)
Oct 2032
Rat Hall Mod App
Solar + storage · Kingsway Solar Farm Limited
700 MWScoping South Anglia Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2034
Sundon Farm 2
Solar + storage · 548 UK Investment Holdings Limited
700 MWScoping Dunstable 400kV Substation
National Grid (England & Wales)
Oct 2032
Page 2 of 12

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.