Grid connection projects in the connection queue on the SP Transmission (south Scotland) network

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown31969.7 GW in total
In planning319scoping or awaiting consent
Consented or building64closest to connecting
Built84connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

319 projects · page 2 of 7
ProjectCapacityStageConnection siteFrom
Hurlet Battery
Battery storage · P-Frequency Ltd
400 MWScoping Neilston 400kV Substation
SP Transmission (south Scotland)
Oct 2033
Kelloe Mains
Battery storage · Tbc 003 Limited
400 MWScoping Kelloe Mains 400kV Substation
SP Transmission (south Scotland)
Nov 2029
Lagrae Battery Storage
Battery storage · Lagrae Battery Storage Limited
400 MWScoping Glenmuckloch 132kV Substation
SP Transmission (south Scotland)
Oct 2036
Lawfield and Branxton Energy Park
Battery storage · Cairn Duhie Energy Limited
400 MWScoping Lawfield and Branxton Energy Park 400kV Substation
SP Transmission (south Scotland)
Jun 2028
Lightsource Auchans
Battery storage · Lightsource Renewable UK Development Limited
400 MWScoping Linwood 400kV Substation
SP Transmission (south Scotland)
Oct 2033
Motherwell 400MW BESS (Formerly Castlehill BESS)
Battery storage · SPV GPC 3 Ltd
400 MWScoping Newarthill 275 kV Substation
SP Transmission (south Scotland)
Apr 2035
Whitelee
Onshore wind · Scottish Power Renewables (UK) Limited
355 MWScoping Whitelee 275/33kV
SP Transmission (south Scotland)
May 2031
Denny BESS
Battery storage · Igp Energy Storage 3 Limited
350 MWScoping Denny North
SP Transmission (south Scotland)
Oct 2030
Westfield BESS
Battery storage · Brockwell Energy Limited
350 MWScoping Westfield 400kV Substation
SP Transmission (south Scotland)
Oct 2031
Blacklaw
Wind + storage · Scottish Power Renewables (UK) Limited
340 MWScoping Blacklaw 132/33kV
SP Transmission (south Scotland)
Oct 2032
Pittlesheugh Farm
Battery storage · Pittlesheugh Farm BESS Limited
340 MWScoping Eccles 400/132kV
SP Transmission (south Scotland)
Oct 2030
High Mathernock Battery Storage
Battery storage · Harmony HM Limited
334 MWScoping High Mathernock 132Kv Substation
SP Transmission (south Scotland)
Oct 2029
Arecleoch
Onshore wind · Scottish Power Renewables (UK) Limited
330 MWScoping Arecleoch 132/33kV
SP Transmission (south Scotland)
Jun 2032
AGS Calderside Battery Energy Storage System
Battery storage · Advance Grid Solutions Limited
300 MWScoping Ags Calderside 275Kv Substation
SP Transmission (south Scotland)
Oct 2029
Aitkenhead Farm BESS
Battery storage · Aitkenhead Storage Facility Limited
300 MWScoping Clydesmill 275/33kV
SP Transmission (south Scotland)
Apr 2033
Boom Power Seaton Hill Generation HUB
Battery storage · Seatonhill Storage Facility Limited
300 MWScoping Cockenzie 400/275kV
SP Transmission (south Scotland)
Oct 2033
Castlemilk 1
Solar · Queequeg Renewables Ltd
300 MWScoping Castlemilk 400kV Substation
SP Transmission (south Scotland)
Oct 2036
Coylton Farm
Battery storage · New Energy Partnership Limited
300 MWAwaiting Consents Coylton 275/33kV Substation
SP Transmission (south Scotland)
Oct 2037
Craig Moss Farm
Battery storage · Qair Renewables UK Limited
300 MWScoping Craig Moss Farm 132kV Substation
SP Transmission (south Scotland)
Oct 2036
Crossgatehall BESS
Battery storage · De 001 Limited
300 MWScoping Smeaton 400/275kV
SP Transmission (south Scotland)
Oct 2033
Elmya Bathgate BESS
Battery storage · Rpc Elmya Carnation Bathgate Limited
300 MWScoping Armadale 400kv Substation
SP Transmission (south Scotland)
Oct 2031
Grangemouth Hybrid BESS & Solar PV
Solar + storage · Tagenergy Development UK Limited
300 MWScoping Letham 400/275kV substation
SP Transmission (south Scotland)
Jun 2032
Gresham House Dalmarnock BESS
Battery storage · Energyhubdevelopments Limited
300 MWScoping Gresham House Dalmarnock Bess 132kv Substation
SP Transmission (south Scotland)
Apr 2030
Gresham House Kincardine BESS
Battery storage · Flavusia Ltd
300 MWScoping Gresham House Kincardine BESS 275/132kV substation
SP Transmission (south Scotland)
Oct 2029
Newarthill Energy Park
Battery storage · Dalzell (Newarthill) Ltd
300 MWScoping Newarthill Energy Park 275kV Substation
SP Transmission (south Scotland)
Oct 2029
Red Moss Farm
Battery storage · Qair Renewables UK Limited
300 MWScoping Red Moss Farm 132kV Substation
SP Transmission (south Scotland)
May 2031
Strathaven BESS
Battery storage · Igp Energy Storage 2 Limited
300 MWScoping Strathaven 400kV Substation
SP Transmission (south Scotland)
Oct 2033
Knarie
Wind + storage · Invenergy Development UK Ltd
297 MWAwaiting Consents Narie 400/132kV Substation
SP Transmission (south Scotland)
Oct 2036
Alcemi Armadale BESS
Battery storage · Alcemi Storage Developments 8 Ltd
280 MWScoping Whitburn 400kV substation
SP Transmission (south Scotland)
Oct 2030
Bodinglee Wind Farm
Wind + storage · Bodinglee Wind Farm Limited
280 MWAwaiting Consents Bodinglee Wind Farm 132kV
SP Transmission (south Scotland)
Apr 2029
KINKHALL266MW BESS BEGA (Kinkell)
Battery storage · Care Power (Kinkhall) Limited
266 MWScoping Kinkell IDNO GSP
SP Transmission (south Scotland)
Apr 2031
Peat Law Renewable Energy Park
Solar + storage · Voltalia UK Ltd
253 MWScoping Peat Law Renewable Energy Park 132kV Substation
SP Transmission (south Scotland)
May 2033
Caple Rig [formerly Faw Side Community Wind Farm]
Onshore wind · Community Windpower Limited
250 MWScoping Caple Rig 132kV Substation
SP Transmission (south Scotland)
Sep 2029
Craigneuk 250MW BESS
Battery storage · Apatura Project 23 Ltd
250 MWScoping Craigneuk 250MW BESS 275kV Substation
SP Transmission (south Scotland)
Oct 2034
Greenock Road BESS
Battery storage · Pulse Clean Energy Limited
250 MWScoping Greenock Road 275kV Substation
SP Transmission (south Scotland)
Oct 2033
Hunterston PARC BESS
Battery storage · Pulse Clean Energy Limited
250 MWScoping Hunterston 400/132kV
SP Transmission (south Scotland)
Oct 2033
TH Renfrewshire
Battery storage · FRV Powertek Limited
250 MWScoping TH Renfrwshire 275kV Substation
SP Transmission (south Scotland)
Oct 2033
West Caulder BESS
Battery storage · GPC Project 13 Ltd
250 MWScoping Harburn 400kV
SP Transmission (south Scotland)
Oct 2033
Ravengill Renewable Energy Park
Solar + storage · Renewco Power Limited
250 MWScoping Elvanfoot 275/132/33kV
SP Transmission (south Scotland)
Oct 2036
Watchman Energy Park
Solar + storage · Renewco Power Limited
250 MWScoping Watchman 132kV Substation
SP Transmission (south Scotland)
Oct 2036
EcoKincardine
Solar + storage · Econergy International Limited
249 MWScoping Kincardine North 400kV Substation
SP Transmission (south Scotland)
Oct 2030
EcoMossmorran
Solar + storage · Econergy International Limited
249 MWScoping Ecomossmorran 400kV Substation
SP Transmission (south Scotland)
Oct 2031
Bearsden BESS
Battery storage · Bearsden BESS Ltd
240 MWScoping Bearsden BESS 275Kv Substation
SP Transmission (south Scotland)
Oct 2033
Burdiehouse BESS
Battery storage · IBV Burdiehouse Energy Park Limited
240 MWScoping Shawfair 400Kv Substation
SP Transmission (south Scotland)
Apr 2034
High Bardrain Wood & Moor
Battery storage · Bluestone Energy Ltd
240 MWScoping High Bardrain Wood & Moor 132Kv Substation
SP Transmission (south Scotland)
Oct 2033
Torness BESS Station
Battery storage · IBV Torness Energy Park Limited
240 MWScoping Thorntonloch 400kV Substation
SP Transmission (south Scotland)
Oct 2031
Bendle Farm
Battery storage · Supernova Power BESS Holdings Limited
228 MWScoping Bendle Farm 132kV Substation
SP Transmission (south Scotland)
Oct 2031
Bendle Farm 2.0
Battery storage · Supernova Power BESS Holdings Limited
228 MWScoping Bendle Farm 2.0 132Kv Substation
SP Transmission (south Scotland)
Oct 2031
Borders Solar
Solar + storage · Buccleuch Estates, Ltd. (The)
228 MWScoping Borders Solar 132/33Kv Substation
SP Transmission (south Scotland)
Oct 2036
Mid Hill
Wind + storage · Invenergy Development UK Ltd
228 MWScoping Mid Hill 132kV Substation
SP Transmission (south Scotland)
Oct 2034

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.