Grid infrastructure βΊ Connection queue βΊ Battery storage
BATTERY STORAGE Β· SPTHurlet Battery
Hurlet Battery is a 400 MW battery storage project in planning, connecting to the SP Transmission (south Scotland) network at Neilston 400kV Substation, with capacity due from October 2033. The connection agreement is held by P-Frequency Ltd.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2033 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-004790
- Customer
- P-Frequency Ltd
- Technology
- Energy Storage System
- Total capacity
- 400 MW
- Change in this agreement
- +400 MW
- Capacity effective from
- 31 October 2033
- Connection site
- Neilston 400kV Substation
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
- Connections reform gate
- Gate 1
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Neilston 400kV Substation
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem