Grid infrastructure β€Ί Connection queue β€Ί Other

OTHER Β· SPT

Neilston Synchronous Compensation

Neilston Synchronous Compensation is a 0 MW other project consented, connecting to the SP Transmission (south Scotland) network at Neilston 400kV Substation, with capacity due from June 2025. The connection agreement is held by Neilston Grid Services Limited.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom Jun 2025 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-001405
Customer
Neilston Grid Services Limited
Technology
Reactive Compensation
Total capacity
0 MW
Capacity effective from
12 June 2025
Connection site
Neilston 400kV Substation
Transmission owner
SP Transmission (south Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Consents Approved

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Neilston Β· Grid map

Other projects at Neilston 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem