| Project | Capacity | Stage |
|---|---|---|
| Ryhall Farm Solar + storage · 548 UK Investment Holdings Limited |
200 MW | Scoping |
| Saltend North BESS & PV Battery storage · Eeb74 Limited |
200 MW | Scoping |
| Saltholme BESS Battery storage · Harmony SH Limited |
200 MW | Scoping |
| Scotton Battery storage · Harmony Energy Limited |
200 MW | Scoping |
| Shurton BESS Battery storage · Field Shurton Ltd |
200 MW | Scoping |
| Stoke Bardolph 400 Solar + storage · Enso Green Holdings Limited |
200 MW | Scoping |
| StrataStore - Cheshire Energy Storage Facility Battery storage · Kistos Energy Storage Ltd |
200 MW | Scoping |
| Sunbury BESS Battery storage · Sunbury BESS Ltd |
200 MW | Scoping |
| Sundon Farm Solar + storage · 548 UK Investment Holdings Limited |
200 MW | Scoping |
| Tewitt Farm BESS Battery storage · Apatura Battery Ltd |
200 MW | Scoping |
| TH Didcot Battery storage · FRV Powertek Limited |
200 MW | Scoping |
| TH Knaresborough Battery storage · FRV Powertek Limited |
200 MW | Scoping |
| TH Maes Melin Battery storage · FRV Powertek Limited |
200 MW | Scoping |
| TH Ninfield Battery storage · FRV Powertek Limited |
200 MW | Scoping |
| TH West Weybridge Battery storage · FRV Powertek Limited |
200 MW | Scoping |
| Thornton BESS Battery storage · Rewe 9 Limited |
200 MW | Scoping |
| Thurcroft Storage Battery storage · Bsr Applications Limited |
200 MW | Scoping |
| Tyler Hill Ansty Battery storage · FRV Tyler Hill BESS 1 Ltd |
200 MW | Scoping |
| UK105-B Upland Arms Solar + storage · Uruk BESS Limited |
200 MW | Scoping |
| Walsoken Battery Battery storage · Walsoken Limited |
200 MW | Scoping |
| Waltham Cross Farm Solar + storage · Waltham Cross 2 Renewables Limited |
200 MW | Scoping |
| Warley Battery Energy Storage Battery storage · London And Essex Energy Limited |
200 MW | Scoping |
| West Melton PV & BESS Station Solar + storage · Ibv West Melton Solar Park Limited |
200 MW | Scoping |
| Worset Lane BESS Battery storage · Field Hartmoor Ltd |
200 MW | Consents Approved |
| Yaxley BESS Battery storage · Field Yaxley Ltd |
200 MW | Scoping |
| Yaxley Farm Solar + storage · 548 UK Investment Holdings Limited |
200 MW | Scoping |
| Thornton Facility Solar + storage · Balwen Limited |
200 MW | Consents Approved |
| Tyler Hill Iver Battery storage · FRV Powertek Limited |
200 MW | Awaiting Consents |
| Manor Farm_Sidcup Battery storage · Firstway Solar Ltd |
200 MW | Scoping |
| Mill Hey_Capenhurst BESS Battery storage · Firstway Solar Ltd |
200 MW | Scoping |
| Deeside Power Station Battery storage · Deeside Power (UK) Limited |
190 MW | |
| Drax Solar + storage · Enso Green Holdings D Limited |
190 MW | Awaiting Consents |
| Llanwern Phase 2 Solar · Future Energy Llanwern Limited |
190 MW | Awaiting Consents |
| Garreg Fawr Energy Park Onshore wind · Garreg Fawr Energy Park Limited |
190 MW | Scoping |
| Tarenni Onshore wind · Tarenni Energy Park Limited |
188 MW | Scoping |
| Menter Mon Morlais Anglesey Marine Energy Other · Menter Môn Morlais Limited |
180 MW | Under Construction/Commissioning |
| NEL Nicholson Battery storage · UE 2 LTD |
180 MW | Scoping |
| North Ray Solar Farm 2 Solar · North Ray Solar Farm 2 Ltd |
180 MW | Scoping |
| Norton Solar Farm Solar · RWE Renewables UK Solar and Storage Limited |
180 MW | Scoping |
| Galileo 06 Onshore wind · Galileo Empower UK Limited |
175 MW | Scoping |
| Merthyr Solar and Battery Solar · Eew Renewables Ltd |
175 MW | Scoping |
| Calderdale Wind Farm 240 MW Onshore wind · Calderdale Wind Farm Ltd |
170 MW | Scoping |
| Elstree Energy Storage Battery storage · Elstree Battery Storage Limited |
170 MW | Scoping |
| Banc y Celyn Energy Park Solar + storage · Parc Ynni Banc Y Celyn Cyf |
165 MW | Scoping |
| Banc y Celyn Energy Park Solar + storage · Wind 2 Project 2 Limited |
165 MW | Scoping |
| Dolyfardyn Onshore wind · Llyn Lort Energy Park Limited |
165 MW | Scoping |
| Oaklands Farm Solar PV Solar + storage · Oaklands Farm Solar Limited. |
162 MW | Consents Approved |
| Derwent Gas · UK Utility Reserve Limited |
162 MW | |
| Garn Fach Wind Farm Wind + storage · Edf Energy Renewables Limited |
162 MW | Scoping |
| Derwent Solar PV Array Solar · Anesco Limited |
160 MW | Scoping |
Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.