Grid infrastructure βΊ Connection queue βΊ Onshore wind
ONSHORE WIND Β· NGETGalileo 06
Galileo 06 is a 175 MW onshore wind project in planning, connecting to the National Grid (England & Wales) network at Llandyfaelog 132kV Substation, with capacity due from October 2037. The connection agreement is held by Galileo Empower UK Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2037 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-003810
- Customer
- Galileo Empower UK Limited
- Technology
- Wind Onshore
- Total capacity
- 175 MW
- Change in this agreement
- +175 MW
- Capacity effective from
- 31 October 2037
- Connection site
- Llandyfaelog 132kV Substation
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Embedded (connects through the local distribution network)
- NESO project status
- Scoping
Connection site
The marker shows the place the connection site is named after, not the project itself, with the transmission network around it.
Other projects at Llandyfaelog 132kV Substation
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem