Grid infrastructure › Connection queue › Battery storage

BATTERY STORAGE · NGET

Tyler Hill Ansty

Tyler Hill Ansty is a 200 MW battery storage project in planning, connecting to the National Grid (England & Wales) network at Warwickshire Connection Node D 132kV Substation, with capacity due from October 2037. The connection agreement is held by FRV Tyler Hill BESS 1 Ltd.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2037 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-004603
Customer
FRV Tyler Hill BESS 1 Ltd
Technology
Energy Storage System
Total capacity
200 MW
Change in this agreement
+200 MW
Capacity effective from
30 October 2037
Connection site
Warwickshire Connection Node D 132kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Scoping

Connection site

This project connects at a new substation (a “connection node”) that has not been built or located yet.

Projects connecting near Warwickshire Connection Node D · Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem