πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

Grid infrastructure β€Ί Connection queue β€Ί Battery storage

BATTERY STORAGE Β· NGET

Worset Lane BESS

Worset Lane BESS is a 200 MW battery storage project consented, connecting to the National Grid (England & Wales) network at Hartmoor 275kV Substation, with capacity due from May 2029. The connection agreement is held by Field Hartmoor Ltd.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom May 2029 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-003650
Customer
Field Hartmoor Ltd
Technology
Energy Storage System
Total capacity
200 MW
Change in this agreement
+200 MW
Capacity effective from
31 May 2029
Connection site
Hartmoor 275kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Consents Approved
Connections reform gate
Gate 2

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Hartmoor Β· Grid map

Other projects at Hartmoor 275kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem