SOLAR + STORAGE · NGETWorset PV & BESS Park
Worset PV & BESS Park is a 38 MW solar + storage project under construction or commissioning, connecting to the National Grid (England & Wales) network at Hartmoor 275kV Substation, with capacity due from October 2027. The connection agreement is held by Worcestershire Solar 1 Limited.
Project stageUnder construction
- Planning (completed)
- Consented (completed)
- Construction (current stage)
- OperatingFrom Oct 2027 (not yet reached)
- Closed (not yet reached)
Connection details
- NESO project number
- PRO-001055
- Customer
- Worcestershire Solar 1 Limited
- Technology
- Energy Storage System, PV Array (Photo Voltaic/solar)
- Total capacity
- 38 MW
- Change in this agreement
- +38 MW
- Capacity effective from
- 30 October 2027
- Connection site
- Hartmoor 275kV Substation
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Under Construction/Commissioning
- Connections reform gate
- Gate 2
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Hartmoor 275kV Substation
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem