πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

Grid infrastructure β€Ί Connection queue β€Ί Onshore wind

ONSHORE WIND Β· NGET

Dolyfardyn

Dolyfardyn is a 165 MW onshore wind project in planning, connecting to the National Grid (England & Wales) network at Chirk GSP, with capacity due from February 2027. The connection agreement is held by Llyn Lort Energy Park Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Feb 2027 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-001584
Customer
Llyn Lort Energy Park Limited
Technology
Wind Onshore
Total capacity
165 MW
Change in this agreement
+165 MW
Capacity effective from
4 February 2027
Connection site
Chirk GSP
Transmission owner
National Grid (England & Wales)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Scoping

Connection site

The connection site could not be placed on the map.

Projects connecting near Chirk GSP Β· Grid map

Other projects at Chirk GSP

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem