Grid infrastructure β€Ί Connection queue β€Ί Onshore wind

ONSHORE WIND Β· NGET

Calderdale Wind Farm 240 MW

Calderdale Wind Farm 240 MW is a 170 MW onshore wind project in planning, connecting to the National Grid (England & Wales) network at Rochdale GSP, with capacity due from October 2037. The connection agreement is held by Calderdale Wind Farm Ltd.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2037 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-004365
Customer
Calderdale Wind Farm Ltd
Technology
Wind Onshore
Total capacity
170 MW
Change in this agreement
+170 MW
Capacity effective from
30 October 2037
Connection site
Rochdale GSP
Transmission owner
National Grid (England & Wales)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Scoping

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Rochdale GSP Β· Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem