Grid infrastructure β€Ί Connection queue β€Ί Gas

GAS Β· NGET

Derwent

Derwent is a 162 MW gas project built and connected, connecting to the National Grid (England & Wales) network at Willington 132kV Substation. The connection agreement is held by UK Utility Reserve Limited.

Project stageOperating
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingApr 2024 (current stage)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-000120
Customer
UK Utility Reserve Limited
Technology
CHP (Combined Heat and Power)
Total capacity
162 MW
Change in this agreement
+162 MW
Capacity effective from
1 April 2024
Connection site
Willington 132kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Built

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Willington Β· Grid map

Other projects at Willington 132kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem