United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESOnshore wind interconnection queue in the USA (2025 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Big Canyon Wind Onshore wind ยท Longfellow Wind, LLC |
1,500 MW | In study |
| Complex Serenity Wind Onshore wind ยท Serenity Wind, LLC |
971 MW | In study |
| Buffalo Jump Wind Onshore wind ยท BOULEVARD ASSOCIATES, LLC |
740 MW | In study |
| Meitner 2 Wind Onshore wind ยท IP Meitner, LLC |
709 MW | In study |
| Commodus 2 Wind Onshore wind ยท IP Blackwell II, LLC |
642 MW | In study |
| Onshore wind project GEN-2024-345, Nowata County Onshore wind |
600 MW | In study |
| Onshore wind project 2025-G3 Onshore wind |
500 MW | In study |
| Onshore wind project ERAS-2025-021, Hale County Onshore wind |
500 MW | In study |
| Onshore wind project J3860, Peoria County Onshore wind |
500 MW | In study |
| Onshore wind project CSUT-2025-1, Lincoln County Onshore wind |
500 MW | In study |
| Onshore wind project 2025-G4 Onshore wind |
500 MW | In study |
| Siete Wind Onshore wind ยท Siete Wind, LLC |
493 MW | In study |
| Onshore wind project J3966, Huron County Onshore wind |
480 MW | In study |
| Alkali Creek Wind Onshore wind ยท Alkali Creek Wind, LLC |
474 MW | In study |
| Serenity Wind Onshore wind ยท Serenity Wind, LLC |
473 MW | In study |
| Red Butte Wind Onshore wind ยท Red Butte Wind, LLC |
457 MW | In study |
| Onshore wind project GEN-2024-141, Mercer County Onshore wind |
424 MW | In study |
| Onshore wind project GEN-2024-102, Finney County Onshore wind |
401 MW | In study |
| Onshore wind project GEN-2024-109, Bailey County Onshore wind |
401 MW | In study |
| Onshore wind project T2-057, Carbon County Onshore wind |
400 MW | In study |
| Onshore wind project 2025-G7 Onshore wind |
400 MW | In study |
| Onshore wind project GEN-2024-221, Roosevelt County Onshore wind |
400 MW | In study |
| Onshore wind project IA-PNM-2025-19, Torrance County Onshore wind |
400 MW | In study |
| Moon Chapel Wind Onshore wind ยท Orsted Onshore Development North America, LLC |
379 MW | In study |
| Viento Bravo Wind Onshore wind ยท Webb Wind, LLC |
367 MW | In study |
| Onshore wind project E0015, Franklin County Onshore wind ยท Interstate Power and Light Company (IPL) |
360 MW | In study |
| Max 4 Wind Onshore wind ยท Lake Creek Wind, LLC |
353 MW | In study |
| Longview Wind Onshore wind ยท Longview Wind, LLC |
353 MW | Agreement signed |
| Onshore wind project J4203, Huron County Onshore wind |
350 MW | In study |
| Onshore wind project J3991, Mclean County Onshore wind |
340 MW | In study |
| Slager Lake Wind Onshore wind ยท NextEra Energy Resources Interconnection Holdings, LLC |
310 MW | In study |
| Onshore wind project J4056, Marshall County Onshore wind |
310 MW | In study |
| Estrella Dorada Wind Onshore wind ยท Estrella Dorada Wind Farm, LLC |
306 MW | In study |
| Prairie Power Wind Onshore wind ยท Prairie Power Wind, LLC |
303 MW | In study |
| Live Oak Wind II Onshore wind ยท ENGIE IR Holdings LLC |
303 MW | In study |
| Barranca Wind 1 Onshore wind ยท Barranca Wind Energy, LLC |
301 MW | In study |
| Onshore wind project 763, Power County Onshore wind |
300 MW | In study |
| Onshore wind project GEN-2024-258, Allen County Onshore wind |
300 MW | In study |
| Onshore wind project GEN-2024-137, Scott County Onshore wind |
300 MW | In study |
| Onshore wind project J3901, Shelby County Onshore wind |
300 MW | In study |
| Onshore wind project GEN-2024-240, Nowata County Onshore wind |
300 MW | In study |
| Onshore wind project GEN-2024-138, Scott County Onshore wind |
300 MW | In study |
| Bendito Wind Onshore wind ยท Bendito Wind Farm, LLC |
300 MW | In study |
| Onshore wind project T2-025, Bingham County Onshore wind |
300 MW | In study |
| Onshore wind project GEN-2024-142, Mcpherson County Onshore wind |
300 MW | In study |
| Onshore wind project J3886, Swift County Onshore wind |
300 MW | In study |
| Onshore wind project J3887, Montcalm County Onshore wind |
300 MW | In study |
| Onshore wind project J3910, Newton County Onshore wind |
300 MW | In study |
| Onshore wind project GEN-2024-144, Scott County Onshore wind |
300 MW | In study |
| Onshore wind project CS25-11, Garfield County Onshore wind |
300 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)36 ยท 13.2 GW
- MISO (Midcontinent)49 ยท 11.4 GW
- SPP (Southwest Power Pool)36 ยท 8,711 MW
- West (non-ISO utilities)26 ยท 6,718 MW
- PJM (Mid-Atlantic, Midwest)3 ยท 468 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)