OCTARY USA ยท INTERCONNECTION QUEUES

Onshore wind interconnection queue in the USA (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown13234.5 GW
Active in queue34.5 GW132 requests
Agreement signed3,006 MW13 requests
Withdrawn7517.7 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

132 requests ยท page 1 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Corvette Wind
Onshore wind
1,200 MWPaused / redesign Carson, TXERCOT Feb 2024
Axis Ridge Wind
Onshore wind ยท Axis Ridge Wind, LLC
750 MWIn study Sutton, TXERCOT Nov 2024target 2029
Commodus Wind
Onshore wind ยท IP Blackwell, LLC
641 MWIn study Briscoe, TXERCOT Jul 2024target 2029
Cavell Wind
Onshore wind ยท IP Cavell, LLC
641 MWIn study Castro, TXERCOT Jul 2024target 2029
Kingsmill Wind SLF
Onshore wind ยท Kingsmill Wind, LLC
606 MWIn study Carson, TXERCOT Jan 2024target 2029
Onshore wind project 5RSC-2024-17, Kit Carson County
Onshore wind
603 MWIn study Kit Carson, COWest Jan 2024target 2026
Sitges Wind
Onshore wind ยท NextEra Energy Interconnection Holdings, LLC
600 MWIn study Motley, TXERCOT Mar 2024target 2029
Onshore wind project 5RSC-2024-29, Yuma County
Onshore wind
554 MWIn study Yuma, COWest Jan 2024target 2027
Tall Saddle Wind
Onshore wind ยท Tall Saddle Wind, LLC
523 MWIn study Kenedy, TXERCOT Jul 2024target 2029
Onshore wind project GI-122, Randolph County
Onshore wind
500 MWIn study Randolph, MOSoutheast May 2024target 2028
Onshore wind project 5RSC-2024-15, Kiowa County
Onshore wind
500 MWIn study Kiowa, COWest Jan 2024target 2027
Onshore wind project 5RSC-2024-28, Kit Carson County
Onshore wind
500 MWIn study Kit Carson, COWest Jan 2024target 2025
Mirando Valley Wind
Onshore wind ยท ACE DevCo NC LLC
479 MWIn study Jim Hogg, TXERCOT Aug 2024target 2028
Onshore wind project 5RSC-2024-16, Cheyenne County
Onshore wind
450 MWIn study Cheyenne, COWest Jan 2024target 2026
Onshore wind project J3730, Macoupin County
Onshore wind
444 MWIn study Macoupin, ILMISO Apr 2024target 2028
Onshore wind project GI-2024-13, Adams County
Onshore wind
423 MWIn study Adams, COWest May 2024target 2028
Onshore wind project GI-2024-12, Adams County
Onshore wind
423 MWIn study Adams, COWest May 2024target 2028
Windecker
Onshore wind ยท Windecker Energy LLC
420 MWIn study Upton, TXERCOT Mar 2024target 2028
Onshore wind project J3712, Peoria County
Onshore wind
400 MWIn study Peoria, ILMISO Apr 2024target 2028
Onshore wind project J3701, Taylor County
Onshore wind
400 MWIn study Taylor, IAMISO Apr 2024target 2028
Onshore wind project PIS089, Lincoln County
Onshore wind
400 MWIn study Lincoln, WYWest Oct 2024target 2028
North Country Wind
Onshore wind ยท NY North Country, LLC
380 MWIn study Franklin, NYNYISO Sep 2024target 2029
North Country Wind II
Onshore wind ยท NY North Country, LLC
380 MWIn study Franklin, NYNYISO Sep 2024target 2029
Paint Rock Wind
Onshore wind ยท Orsted Onshore Development North America, LLC
379 MWIn study Concho, TXERCOT Jan 2024target 2028
Skyrider Wind
Onshore wind ยท NextEra Energy Interconnection Holdings, LLC
370 MWIn study Pecos, TXERCOT Nov 2024target 2028
West Munday Wind
Onshore wind ยท Lake Creek Wind, LLC
352 MWAgreement signed Knox, TXERCOT Nov 2024target 2028
Onshore wind project J3623, Sunflower County
Onshore wind
350 MWIn study Sunflower, MSMISO Apr 2024target 2028
Onshore wind project J3521, Shelby County
Onshore wind
350 MWIn study Shelby, ILMISO Apr 2024target 2028
Onshore wind project GI-TC-2024-25, Weld County
Onshore wind
350 MWIn study Weld, COWest May 2024target 2028
Onshore wind project J3597, Lonoke County
Onshore wind
348 MWIn study Lonoke, ARMISO Apr 2024target 2028
Onshore wind project J3798, Winnebago County
Onshore wind
320 MWIn study Winnebago, IAMISO Mar 2024target 2028
Onshore wind project J3982, Lonoke County
Onshore wind
320 MWIn study Lonoke, ARMISO Dec 2024target 2030
Bullring Wind 2
Onshore wind ยท Halcon Wind, LLC
304 MWAgreement signed Starr, TXERCOT May 2024target 2028
Bullring Wind 1
Onshore wind ยท Halcon Wind, LLC
304 MWAgreement signed Starr, TXERCOT May 2024target 2028
Ciervo Wind
Onshore wind ยท RWE Clean Energy Development, LLC
302 MWIn study Jim Hogg, TXERCOT Dec 2024target 2028
Onshore wind project GEN-2025-GR1, Grant County
Onshore wind
300 MWIn study Grant, OKSPP Dec 2024target 2027
Onshore wind project GI-123, Craig County
Onshore wind
300 MWIn study Craig, OKSoutheast Sep 2024target 2027
Onshore wind project J3699, Henry County
Onshore wind
300 MWIn study Henry, ILMISO Apr 2024target 2028
Onshore wind project 2024-G5, Mohave County
Onshore wind
300 MWIn study Mohave, AZWest Aug 2024target 2029
Onshore wind project J3681, Mclean County
Onshore wind
300 MWIn study Mclean, ILMISO Apr 2024target 2028
Onshore wind project J3866, Lapeer County
Onshore wind
300 MWIn study Lapeer, MIMISO Dec 2024target 2028
Onshore wind project GEN-2024-016, Smith County
Onshore wind
300 MWIn study Smith, KSSPP Oct 2024target 2028
Onshore wind project J3384, Big Stone County
Onshore wind
300 MWIn study Big Stone, MNMISO Apr 2024target 2028
Onshore wind project J3853, Iroquois County
Onshore wind
300 MWIn study Iroquois, ILMISO Dec 2024target 2029
Onshore wind project J3672, Big Stone County
Onshore wind
300 MWIn study Big Stone, MNMISO Apr 2024target 2028
Onshore wind project GEN-2024-GR6, Kay County
Onshore wind
300 MWIn study Kay, OKSPP Jul 2024target 2027
Onshore wind project J3280, Dickey County
Onshore wind
300 MWIn study Dickey, NDMISO Apr 2024target 2028
Sanders Hollow Energy Center
Onshore wind ยท Sanders Hollow Energy Center, LLC
293 MWIn study Dickens, TXERCOT Oct 2024target 2028
Windjammer Windpower
Onshore wind ยท Windjammer Windpower, LLC
293 MWAgreement signed Glasscock, TXERCOT Sep 2024target 2028
Onshore wind project 5RSC-2024-18, Prowers County
Onshore wind
293 MWIn study Prowers, COWest Jan 2024target 2029
Page 1 of 3

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)