United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2015 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Other project PQ0002, Cerro Gordo County Other |
2,000 MW | Withdrawn / abandoned |
| Gas project AB1-003, Indiana County Gas |
1,474 MW | Withdrawn / abandoned |
| Eagle Mountain Pump Storage #4 Battery storage |
1,408 MW | Withdrawn / abandoned |
| Gas project AA2-142, Somerset County Gas |
1,377 MW | Withdrawn / abandoned |
| Gas project J433, Union County Gas |
1,270 MW | Withdrawn / abandoned |
| Gas project J480, Cherokee County Gas |
1,240 MW | Withdrawn / abandoned |
| Gas project 267, Davidson County Gas |
1,220 MW | Withdrawn / abandoned |
| Gas project J434, Vermillion County Gas |
1,185 MW | Withdrawn / abandoned |
| Gas project J435, Eau Claire County Gas |
1,185 MW | Withdrawn / abandoned |
| Mason Energy Center Gas |
1,150 MW | Withdrawn / abandoned |
| Gas project AA2-109, Lancaster County Gas |
1,100 MW | Withdrawn / abandoned |
| Gas project AB1-154, Hunterdon County Gas |
1,092 MW | Withdrawn / abandoned |
| Gas project AB1-153, Adams County Gas |
1,062 MW | Withdrawn / abandoned |
| Clear River Gas |
1,030 MW | Withdrawn / abandoned |
| Gas project AA2-182, Snyder County Gas |
1,030 MW | Withdrawn / abandoned |
| Beech Hollow Energy Center Gas |
1,025 MW | Withdrawn / abandoned |
| Combined Cycle Gas |
1,020 MW | Withdrawn / abandoned |
| Liberty Generation Gas ยท North Bergen Liberty Generation Center LLC |
1,000 MW | Withdrawn / abandoned |
| Gas project J487, San Jacinto County Gas |
999 MW | Withdrawn / abandoned |
| Gas project J539, Newton County Gas |
999 MW | Withdrawn / abandoned |
| Gas project AB1-175, Clearfield County Gas |
989 MW | Withdrawn / abandoned |
| Cedar Point Energy Center Gas |
955 MW | Withdrawn / abandoned |
| Gas project 266, Davidson County Gas |
940 MW | Withdrawn / abandoned |
| Gas project GEN-2015-051, Lyon County Gas |
916 MW | Withdrawn / abandoned |
| Gas project AB1-002, Middlesex County Gas |
909 MW | Withdrawn / abandoned |
| Combined Cycle Gas |
870 MW | Withdrawn / abandoned |
| Combined Cycle Gas |
870 MW | Withdrawn / abandoned |
| ESC Brooke County Power I Gas |
685 MW | Withdrawn / abandoned |
| Morro Bay Wave Energy Project Other |
650 MW | Withdrawn / abandoned |
| Hecate McCamey C Solar Solar ยท Hecate Energy |
600 MW | Withdrawn / abandoned |
| Irish Gas |
600 MW | Withdrawn / abandoned |
| Onshore wind project J462, Emmet County Onshore wind |
598 MW | Withdrawn / abandoned |
| Gas project AA2-125, Middlesex County Gas |
580 MW | Withdrawn / abandoned |
| Gas project AA2-124, Middlesex County Gas |
576 MW | Withdrawn / abandoned |
| Byron to Wayne Thermal #1 Project Gas |
575 MW | Withdrawn / abandoned |
| Gas project AB1-091, Kankakee County Gas |
575 MW | Withdrawn / abandoned |
| Gas project AB1-086, Mclean County Gas |
575 MW | Withdrawn / abandoned |
| Gas project AB1-151, Wayne County Gas |
575 MW | Withdrawn / abandoned |
| Gas project AB1-169A, Atlantic County Gas |
575 MW | Withdrawn / abandoned |
| Gas project AB1-090, Lee County Gas |
575 MW | Withdrawn / abandoned |
| Energy Center Gas |
570 MW | Withdrawn / abandoned |
| Gas project AA2-111, Lancaster County Gas |
550 MW | Withdrawn / abandoned |
| Tioga County Power Gas ยท ESC Tioga County Power, LLC |
550 MW | Withdrawn / abandoned |
| Gas project AA2-110, Delaware County Gas |
550 MW | Withdrawn / abandoned |
| Panda Sherman 2 G Gas ยท Panda Funds |
543 MW | Withdrawn / abandoned |
| Allegheny Energy Center LLC Gas |
541 MW | Withdrawn / abandoned |
| Rainbow Energy Center Gas |
523 MW | Withdrawn / abandoned |
| Midtown Canyon Gas Gas |
507 MW | Withdrawn / abandoned |
| Renovo Energy Center Gas ยท Renovo Energy Center, LLC |
504 MW | Withdrawn / abandoned |
| Onshore wind project J439, Emmet County Onshore wind |
500 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- PJM (Mid-Atlantic, Midwest)231 ยท 27.2 GW
- MISO (Midcontinent)53 ยท 17.2 GW
- CAISO (California)91 ยท 12.3 GW
- SPP (Southwest Power Pool)72 ยท 11.1 GW
- ISO-NE (New England)46 ยท 7,500 MW
- West (non-ISO utilities)197 ยท 6,025 MW
- ERCOT (Texas)28 ยท 5,278 MW
- Southeast (non-ISO utilities)49 ยท 4,719 MW
- NYISO (New York)33 ยท 4,251 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)