United States β€Ί Grid β€Ί Interconnection queues β€Ί New Jersey

GAS Β· PJM

Gas project AA2-124, Middlesex County

Gas project AA2-124, Middlesex County is a 576 MW gas request withdrawn in the PJM interconnection queue, in Middlesex County, New Jersey, connecting to PSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2015 (completed)
  2. Withdrawn / abandonedSep 2015 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AA2-124
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Sewaren 230kV
Location
Middlesex County, New Jersey
Technology
Gas: 576 MW
Total requested
576 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study
Queue status
Withdrawn
Entered queue
29 April 2015
Proposed online date
May 2019
Withdrawn
September 2015

Location

Marker shows the centre of Middlesex County; the queue data does not give exact sites.