🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New Jersey

GAS · PJM

Woodbridge Energy Center

Woodbridge Energy Center is a 725 MW gas request built and operating in the PJM interconnection queue, in Middlesex County, New Jersey, connecting to JCPL.

Queue statusOperating
  1. PlanningQueued Nov 2010 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2015 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
W4-009
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
JCPL
Connection point (POI)
Raritan River 230kV
Location
Middlesex County, New Jersey
Technology
Gas: 725 MW
Total requested
725 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
22 November 2010
Proposed online date
June 2017
Came online
December 2015

Location

Marker shows the centre of Middlesex County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Middlesex County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem