πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

SOLAR Β· ERCOT

Hecate McCamey C Solar

Hecate McCamey C Solar is a 600 MW solar request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2015 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
16INR0110
Grid region
ERCOT (Texas)
Developer
Hecate Energy
Connection point (POI)
North McCamey 345kV (76000)
Technology
Solar: 600 MW
Total requested
600 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
13 May 2015
Proposed online date
July 2016

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem