Renovo Energy Center

Renovo Energy Center is a 504 MW gas request withdrawn in the NYISO interconnection queue, in Clinton County, Pennsylvania, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2015 (completed)
  2. Withdrawn / abandonedFeb 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
496
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
Renovo Energy Center, LLC
Connection point (POI)
Homer City - Mainsburg 345kV
Location
Clinton County, Pennsylvania
Technology
Gas: 504 MW
Total requested
504 MW
Queue status
Withdrawn
Entered queue
13 April 2015
Withdrawn
February 2021

Location

Marker shows the centre of Clinton County; the queue data does not give exact sites.