Renovo Energy Center Uprate

Renovo Energy Center Uprate is a 548 MW gas request withdrawn in the NYISO interconnection queue, in Clinton County, Pennsylvania, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2018 (completed)
  2. Withdrawn / abandonedJan 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
693
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
Renovo Energy Center, LLC
Connection point (POI)
Homer City - Mainesburg 345kV
Location
Clinton County, Pennsylvania
Technology
Gas: 548 MW
Total requested
548 MW
Queue status
Withdrawn
Entered queue
13 February 2018
Withdrawn
January 2023

Location

Marker shows the centre of Clinton County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Clinton County