United States βΊ Grid βΊ Interconnection queues βΊ Pennsylvania
SOLAR Β· NYISOWinner Solar
Winner Solar is a 120 MW solar request withdrawn in the NYISO interconnection queue, in Clinton County, Pennsylvania, connecting to NYSEG.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2022 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1404
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYSEG
- Developer
- Winner Solar, LLC
- Connection point (POI)
- Homer City - Mainesburg 345kV
- Location
- Clinton County, Pennsylvania
- Technology
- Solar: 120 MW
- Total requested
- 120 MW
- Queue status
- Withdrawn
- Entered queue
- 14 July 2022
Location
Marker shows the centre of Clinton County; the queue data does not give exact sites.
Power plants in Pennsylvania Β· Transmission lines in Pennsylvania
Other requests in Clinton County
- Renovo Energy Center UprateGas Β· 548 MW Β· withdrawn
- Renovo Energy CenterGas Β· 504 MW Β· withdrawn
- Renovo Energy CenterGas Β· 463 MW Β· withdrawn
- Battery storage project AF2-411, Clinton CountyBattery storage Β· 300 MW Β· withdrawn
- Solar project AF1-172, Clinton CountySolar Β· 250 MW Β· withdrawn
- Winner SolarSolar Β· 120 MW Β· withdrawn
- Gas project AF1-043, Clinton CountyGas Β· 105 MW Β· withdrawn
- Coal project T162, Clinton CountyCoal Β· 90.0 MW Β· withdrawn
- Renovo Energy CenterGas Β· 44.0 MW Β· withdrawn
- Renovo Energy CenterGas Β· 41.0 MW Β· withdrawn
- Onshore wind project Q40, Clinton CountyOnshore wind Β· 40.0 MW Β· withdrawn
- Other project AD1-111, Clinton CountyOther Β· 4.1 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem