🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Pennsylvania

GAS · PJM

Beech Hollow Energy Center

Beech Hollow Energy Center is a 1,025 MW gas request withdrawn in the PJM interconnection queue, in Washington County, Pennsylvania, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2015 (completed)
  2. Withdrawn / abandonedMar 2021 (project stopped here)
  3. ConsentedDec 2017 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AB1-069
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Wylie Ridge 500kV
Location
Washington County, Pennsylvania
Technology
Gas: 1,025 MW
Total requested
1,025 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Withdrawn
Entered queue
9 September 2015
Agreement signed
4 December 2017
Proposed online date
February 2023
Withdrawn
March 2021

Location

Marker shows the centre of Washington County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Washington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem