Beech Hollow Energy Center is a 1,025 MW gas request withdrawn in the PJM interconnection queue, in Washington County, Pennsylvania, connecting to APS.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2015 (completed)
- Withdrawn / abandonedMar 2021 (project stopped here)
- ConsentedDec 2017 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AB1-069
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Connection point (POI)
- Wylie Ridge 500kV
- Location
- Washington County, Pennsylvania
- Technology
- Gas: 1,025 MW
- Total requested
- 1,025 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Withdrawn
- Entered queue
- 9 September 2015
- Agreement signed
- 4 December 2017
- Proposed online date
- February 2023
- Withdrawn
- March 2021
Location
Marker shows the centre of Washington County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Washington County
- Cornerstone SolarSolar · 200 MW · in study
- Smith-Francis Junction 25 kVSolar · 20.0 MW · built
- Gaucho SolarSolar · 11.7 MW · built
- Gaucho SolarSolar · 8.3 MW · built
- Other project P34, Washington CountyOther · 6.4 MW · built
- Gas project Z2-064, Washington CountyGas · 651 MW · withdrawn
- Gas project Y3-042, Washington CountyGas · 460 MW · withdrawn
- Coal project N40, Washington CountyCoal · 300 MW · withdrawn
- Beech HollowGas · 150 MW · withdrawn
- Gas project AA2-043, Washington CountyGas · 99.0 MW · withdrawn
- Gas project AE1-080, Washington CountyGas · 80.0 MW · withdrawn
- Onshore wind project N37, Washington CountyOnshore wind · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem