Smith-Francis Junction 25 kV

Smith-Francis Junction 25 kV is a 20.0 MW solar request built and operating in the PJM interconnection queue, in Washington County, Pennsylvania, connecting to APS.

Queue statusOperating
  1. PlanningQueued Oct 2020 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJul 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AG1-386
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Smith-Francis Junction 25 kV
Location
Washington County, Pennsylvania
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Operational
Entered queue
2 October 2020
Proposed online date
June 2025
Came online
July 2025

Location

Marker shows the centre of Washington County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Washington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem