United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESOnshore wind projects with signed interconnection agreements in the USA
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project GI-83, Randolph County Onshore wind |
1,018 MW | Agreement signed |
| Heritage Prairie Wind Onshore wind |
850 MW | Agreement signed |
| Meitner Wind Onshore wind ยท IP Meitner, LLC |
709 MW | Agreement signed |
| Aurelius Wind Onshore wind ยท IP Roman Wind, LLC |
622 MW | Agreement signed |
| Onshore wind project GI-2016-3, Lincoln County Onshore wind |
600 MW | Agreement signed |
| Onshore wind project 82, Meagher County Onshore wind |
600 MW | Agreement signed |
| Onshore wind project GEN-2016-119, Kingfisher County Onshore wind |
600 MW | Agreement signed |
| Dundee East A Wind Onshore wind ยท Felix 2, LLC |
524 MW | Agreement signed |
| Onshore wind project C1-35, Carbon County Onshore wind ยท Lucky Star Wind, LLC |
500 MW | Agreement signed |
| Onshore wind project GI-2016-14, Cheyenne County Onshore wind |
500 MW | Agreement signed |
| Siete Onshore wind ยท Apex Clean Energy |
493 MW | Agreement signed |
| Whitehorse Wind Onshore wind ยท MESQUITE STAR SPECIAL LLC |
419 MW | Agreement signed |
| Onshore wind project IA-PNM-2016-02, Torrance Cty County Onshore wind ยท Pacific Wind Development |
402 MW | Agreement signed |
| Onshore wind project GEN-2017-183, Hodgeman County Onshore wind |
400 MW | Agreement signed |
| Onshore wind project GI-2006-1g, Logan County Onshore wind |
400 MW | Agreement signed |
| Mount Laguna Wind 2 Onshore wind |
400 MW | Agreement signed |
| Onshore wind project J1026, Audrain County Onshore wind |
400 MW | Agreement signed |
| Onshore wind project GI-TC-2024-16, Laramie County Onshore wind |
400 MW | Agreement signed |
| Onshore wind project 836, Carbon County Onshore wind ยท PacifiCorp |
400 MW | Agreement signed |
| Bug Tussle Wind Project Onshore wind ยท Bug Tussle Wind, LLC |
397 MW | Agreement signed |
| Longview Wind Onshore wind ยท Longview Wind, LLC |
353 MW | Agreement signed |
| West Munday Wind Onshore wind ยท Lake Creek Wind, LLC |
352 MW | Agreement signed |
| Onshore wind project GEN-2016-141, Texas County Onshore wind |
350 MW | Agreement signed |
| Onshore wind project GEN-2016-142, Texas County Onshore wind |
350 MW | Agreement signed |
| Panther Grove Wind Onshore wind |
350 MW | Agreement signed |
| Baird North Wind Onshore wind ยท BMP Wind, LLC |
340 MW | Agreement signed |
| Canyon Wind Onshore wind ยท Canyon Wind Energy, LLC |
309 MW | Agreement signed |
| Laurel Wind Energy Center Onshore wind ยท LAUREL ENERGY CENTER, LLC |
307 MW | Agreement signed |
| Bullring Wind 2 Onshore wind ยท Halcon Wind, LLC |
304 MW | Agreement signed |
| Bullring Wind 1 Onshore wind ยท Halcon Wind, LLC |
304 MW | Agreement signed |
| Priddy Wind Onshore wind ยท ENGIE North America |
302 MW | Agreement signed |
| Onshore wind project GEN-2016-111, Mcpherson County Onshore wind |
302 MW | Agreement signed |
| El Sauz Ranch Onshore wind ยท El Sauz Ranch Wind, LLC |
302 MW | Agreement signed |
| Onshore wind project 83, Meagher County Onshore wind |
300 MW | Agreement signed |
| Onshore wind project GI-2006-1i, Weld County Onshore wind |
300 MW | Agreement signed |
| Onshore wind project J1360, Piatt County Onshore wind |
300 MW | Agreement signed |
| Onshore wind project GI-2016-4, Lincoln County Onshore wind |
300 MW | Agreement signed |
| Onshore wind project J982, Dickinson County Onshore wind |
300 MW | Agreement signed |
| Panther Grove 2 Onshore wind |
300 MW | Agreement signed |
| Onshore wind project GEN-2017-014, Haakon County Onshore wind |
300 MW | Agreement signed |
| Onshore wind project BHBE G13, Custer County Onshore wind |
300 MW | Agreement signed |
| Onshore wind project GEN-2021-056, Harper County Onshore wind |
300 MW | Agreement signed |
| Onshore wind project J1025, Knox County Onshore wind |
300 MW | Agreement signed |
| Onshore wind project GEN-2017-151, Crosby County Onshore wind |
300 MW | Agreement signed |
| Onshore wind project GEN-2018-099, Parmer County Onshore wind |
300 MW | Agreement signed |
| Onshore wind project J1773, Lafayette County Onshore wind |
300 MW | Agreement signed |
| Onshore wind project GEN-2017-181, Lancaster County Onshore wind |
300 MW | Agreement signed |
| Onshore wind project MPC04000, Oliver County Onshore wind |
300 MW | Agreement signed |
| Board Creek Wind Onshore wind ยท Limestone Wind Project, LLC |
299 MW | Agreement signed |
| Firelands Wind Onshore wind |
298 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)71 ยท 15.3 GW
- SPP (Southwest Power Pool)60 ยท 12.1 GW
- West (non-ISO utilities)54 ยท 11.8 GW
- MISO (Midcontinent)21 ยท 4,097 MW
- PJM (Mid-Atlantic, Midwest)19 ยท 3,588 MW
- Southeast (non-ISO utilities)6 ยท 1,849 MW
- CAISO (California)9 ยท 1,144 MW
- ISO-NE (New England)2 ยท 22.9 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)