United States › Grid › Interconnection queues › Texas
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in Texas (2021 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Blue Bird Solar Solar · Gigawatt Solar LLC |
773 MW | Agreement signed |
| Texpo Gas · Oklaunion Power Station, LLC |
680 MW | In study |
| Dovetail Solar 3 Solar + storage · Hecate Energy Dovetail Solar Holdings LLC |
666 MW | In study |
| Dovetail Solar 1 Solar + storage · Hecate Energy Dovetail Solar 1 LLC |
666 MW | In study |
| Dovetail Solar 2 Solar + storage · Hecate Energy Dovetail Solar 2 LLC |
666 MW | In study |
| Hiru Solar Solar + storage · Hecate Energy Hazel LLC |
604 MW | In study |
| Elmax Power Station Gas · Elmax Generating, LLC |
519 MW | Agreement signed |
| Bayside Solar Solar |
509 MW | Paused / redesign |
| Dovetail Storage Solar + storage · Hecate Energy Dovetail Storage LLC |
509 MW | In study |
| Outpost Storage Solar + storage · Hecate Energy Outpost Storage LLC |
508 MW | In study |
| Tehuacana Creek Solar Solar + storage · Tehuacana Creek Solar LLC |
505 MW | Agreement signed |
| Harley Hand Storage Solar + storage · Hecate Energy Harley Hand Solar LLC |
503 MW | In study |
| Calpine Guadalupe Peakers Gas · Guadalupe Peaking Energy Center, LLC |
450 MW | In study |
| Poco Trail Solar Solar · Eastern Trail Solar Center, LLC |
439 MW | In study |
| BRP Artemis BESS Battery storage · BRP Artemis BESS LLC |
411 MW | In study |
| BRP Snowdon BESS Battery storage · BRP SNOWDON BESS LLC |
411 MW | In study |
| BRP Mekong BESS Battery storage · BRP Mekong BESS LLC |
410 MW | In study |
| Beacon Storage Battery storage · AES Distributed Energy, Inc |
409 MW | In study |
| Sigma Storage Battery storage · AES Distributed Energy, Inc |
408 MW | In study |
| Grasshopper Solar Solar · Grasshopper Solar LLC |
408 MW | In study |
| Compadre Solar Solar · Hill Solar I, LLC |
406 MW | Agreement signed |
| Merope BESS Battery storage · BRP Merope BESS LLC |
402 MW | In study |
| Solar + storage project GEN-2021-090, Yoakum County Solar + storage |
400 MW | In study |
| Briggs Storage Solar + storage · IP Quantum III, LLC |
336 MW | Agreement signed |
| Platinum Storage Battery storage · Platinum Energy Storage LLC |
310 MW | Agreement signed |
| Larkspur Energy Storage Battery storage · Larkspur Energy Storage LLC |
308 MW | Agreement signed |
| Cuchillas Solar Solar + storage · Gransolar Texas Two, LLC |
306 MW | Agreement signed |
| BRP Aras BESS Battery storage · BRP Aras BESS LLC |
304 MW | In study |
| Jaguar Solar Solar + storage · PP Jaguar Solar LLC |
301 MW | Agreement signed |
| Pachanga Wind Onshore wind · Pachanga Wind LLC |
300 MW | In study |
| SP Jaguar BESS Other · PP Jaguar BESS LLC |
300 MW | Paused / redesign |
| Aquilla Lake 3 Wind Onshore wind · Aquilla Lake 3 Wind |
297 MW | Agreement signed |
| Blevins Solar Solar · Blevins Solar, LLC |
272 MW | Agreement signed |
| OCI SunRoper Solar · OCI SunRoper LLC |
265 MW | Agreement signed |
| Possum Kingdom Solar Solar + storage · PK Solar, LLC |
262 MW | In study |
| Yellow Cat Wind Onshore wind · Yellow Cat Wind LLC |
262 MW | Agreement signed |
| Miranda Solar Project Solar · Miranda Solar Project, LLC |
261 MW | Agreement signed |
| Sypert Branch Solar Project Solar · Sypert Branch Solar LLC |
261 MW | Agreement signed |
| Zeya BESS Battery storage · BRP Zeya BESS LLC |
255 MW | Agreement signed |
| Maleza Solar II Solar + storage · Brush Solar, LLC |
255 MW | In study |
| Roseland Solar II Solar · Enel Green Power Roseland Solar, LLC |
254 MW | Agreement signed |
| Bayside II Solar Solar |
253 MW | Paused / redesign |
| Tiger Storage Battery storage |
251 MW | Paused / redesign |
| Tiger Solar Solar · Vaca Del Sol, LLC |
251 MW | Agreement signed |
| Cascade Storage Battery storage |
250 MW | Paused / redesign |
| Lupinus Solar 2 Solar + storage · Lupinus Solar 2, LLC |
242 MW | Agreement signed |
| Campsey Wind Onshore wind · RWE Clean Energy Development, LLC |
238 MW | In study |
| DeSpain Solar Project Solar · Gransolar Texas Thirteen LLC |
236 MW | In study |
| Utley Solar Solar |
222 MW | Paused / redesign |
| Goodalta Solar Solar · GoodAlta Power Center LLC |
221 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)