United States › Grid › Interconnection queues › Texas
OCTARY USA · INTERCONNECTION QUEUESCompleted queue projects in Texas
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project J472, Montgomery County Gas |
1,045 MW | |
| Hornet Solar Solar · Hornet Solar LLC |
602 MW | |
| Aviator Wind Onshore wind · Apex Clean |
525 MW | |
| Frontera Energy Center Gas · Frontera Generation Limited Partnership |
524 MW | |
| Plainview Solar Solar · Hecate Energy Ramsey LLC |
514 MW | |
| Topaz Power Plant Gas · Topaz Generating, LLC |
510 MW | |
| Frye Solar Solar + storage · Hecate Energy |
502 MW | |
| Young Wind Onshore wind · Young Wind, LLC |
499 MW | |
| Parliament Solar Solar · Parliament Solar LLC |
485 MW | |
| Onshore wind project GEN-2012-020, Hale County Onshore wind |
478 MW | |
| High Lonesome Wind Onshore wind · Enel |
450 MW | |
| Eunice Solar Solar · 2W Permian Solar LLC |
427 MW | |
| Montana Units 1-4 (Gas) Gas |
420 MW | |
| Ash Creek Solar Solar · Ash Creek Solar LLC |
418 MW | |
| Apogee Wind Onshore wind · EDF Renewables Development, Inc. |
393 MW | |
| Maverick Creek I Wind Onshore wind · Maverick Creek Wind, LLC |
373 MW | |
| Onshore wind project GEN-2006-044, Hansford County Onshore wind |
370 MW | |
| Ajax Wind Onshore wind · Lincoln Clean |
367 MW | |
| Onshore wind project GEN-2010-014, Hansford County Onshore wind |
359 MW | |
| Hollywood Solar Solar · Red Tailed Hawk Solar LLC |
353 MW | |
| Vortex Wind Onshore wind · AZURE SKY WIND PROJECT LLC |
350 MW | |
| Foard City Wind Onshore wind · Innergex |
350 MW | |
| White Mesa 2 Wind Onshore wind · White Mesa Wind, LLC |
348 MW | |
| Sage Draw Wind Onshore wind · Lincoln Clean |
338 MW | |
| TG East Wind Onshore wind · Northrenew |
336 MW | |
| Radian Solar Solar + storage · IP Radian, LLC |
327 MW | |
| Andromeda Solar Solar · IP Renewable Energy Holdings LLC |
327 MW | |
| Jade Solar Solar · IP RENEWABLE ENERGY HOLDINGS LLC |
327 MW | |
| Five Wells Solar Solar · Five Wells Solar Center LLC |
323 MW | |
| Onshore wind project GEN-2014-040, Castro County Onshore wind |
320 MW | |
| Jarvis BESS Other · SMT Ironman BESS LLC |
308 MW | |
| Tierra Bonita Solar Solar · Greasewood II LLC |
307 MW | |
| PES1 Gas · HO CLARKE GENERATING LLC |
306 MW | |
| Remy Jade Power Station Gas · Remy Jade Generating, LLC |
306 MW | |
| Photon Storage Other · GulfStar Power, LLC |
306 MW | |
| Bright Arrow Solar Solar · RWE Solar Development, LLC |
305 MW | |
| Lacy Creek wind Wind + storage · Lacy Creek Wind, LLC |
301 MW | |
| Peregrine Solar Solar + storage · SP-Peregrine Solar LLC |
301 MW | |
| Inertia Wind Onshore wind · Inertia Wind Project, LLC |
301 MW | |
| Rodeo Ranch Energy Storage Other · Rodeo Ranch Energy Storage, LLC |
301 MW | |
| Torrecillas Wind Onshore wind · Nextera |
301 MW | |
| Tahoka Wind Onshore wind · Lincoln Clean |
300 MW | |
| Prospero Solar*** Solar · Longroad Energy |
300 MW | |
| Ranchero Wind Onshore wind · Scout Clean Energy |
300 MW | |
| Oveja Wind Onshore wind · Invenergy |
300 MW | |
| Onshore wind project GEN-2011-022, Hansford County Onshore wind |
299 MW | |
| Noble Solar Solar · BT Noble Solar, LLC |
279 MW | |
| Las Majadas Wind Onshore wind · EDF Renewable Energy |
273 MW | |
| Titan Solar Solar · SE Titan, LLC |
270 MW | |
| Tanzanite Storage Battery storage · Tanzanite Energy Storage LLC |
266 MW |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)397 · 53.8 GW
- SPP (Southwest Power Pool)30 · 4,859 MW
- MISO (Midcontinent)3 · 1,246 MW
- West (non-ISO utilities)1 · 420 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)