Torrecillas Wind

Torrecillas Wind is a 301 MW onshore wind request built and operating in the ERCOT interconnection queue, in Webb County, Texas.

Queue statusOperating
  1. PlanningQueued Jan 2013 (completed)
  2. ConsentedApr 2018 (completed)
  3. Construction (completed)
  4. OperatingNov 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
14INR0045
Grid region
ERCOT (Texas)
Developer
Nextera
Connection point (POI)
161252, 161301 Torrecillas 34.5kV
Location
Webb County, Texas
Technology
Wind: 301 MW
Total requested
301 MW
Study phase
IA
Queue status
Operational
Entered queue
29 January 2013
Agreement signed
12 April 2018
Proposed online date
November 2019
Came online
November 2019

Location

Marker shows the centre of Webb County; the queue data does not give exact sites.