🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Peregrine Solar

Peregrine Solar is a 301 MW solar + storage request built and operating in the ERCOT interconnection queue, in Goliad County, Texas.

Queue statusOperating
  1. PlanningQueued Jan 2020 (completed)
  2. ConsentedJun 2021 (completed)
  3. Construction (completed)
  4. OperatingNov 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0283
Grid region
ERCOT (Texas)
Developer
SP-Peregrine Solar LLC
Connection point (POI)
tap 345kV 8624 Grissom – 8164 Coleto Creek
Location
Goliad County, Texas
Technology
Solar: 301 MW · Battery
Total requested
301 MW
Study phase
IA
Queue status
Operational
Entered queue
6 January 2020
Agreement signed
19 June 2021
Proposed online date
July 2025
Came online
November 2024

Location

Marker shows the centre of Goliad County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Goliad County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem