United States › Grid › Interconnection queues › Texas
SOLAR + STORAGE · ERCOTPeregrine Solar
Peregrine Solar is a 301 MW solar + storage request built and operating in the ERCOT interconnection queue, in Goliad County, Texas.
Request details
- Queue ID
- 22INR0283
- Grid region
- ERCOT (Texas)
- Developer
- SP-Peregrine Solar LLC
- Connection point (POI)
- tap 345kV 8624 Grissom – 8164 Coleto Creek
- Location
- Goliad County, Texas
- Technology
- Solar: 301 MW · Battery
- Total requested
- 301 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 6 January 2020
- Agreement signed
- 19 June 2021
- Proposed online date
- July 2025
- Came online
- November 2024
Location
Marker shows the centre of Goliad County; the queue data does not give exact sites.
Other requests in Goliad County
- Tulsita SolarSolar · 256 MW · agreement signed
- Keys Hollow Solar Phase II SLFSolar + storage · 204 MW · agreement signed
- Keys Hollow Solar SLFSolar + storage · 204 MW · agreement signed
- Coleto Creek - Fuel Change OnlyGas · 655 MW · in study
- Diablo Campo StorageBattery storage · 314 MW · in study
- Kuy Creek Solar 1 SLFSolar + storage · 235 MW · in study
- Angel City SolarSolar · 221 MW · in study
- Eighteenmile Solar SLFSolar + storage · 153 MW · in study
- Kuy Creek Storage 1 SLFSolar + storage · 152 MW · in study
- Peregrine BESSSolar + storage · 150 MW · in study
- Peregrine BESS 2Solar + storage · 150 MW · in study
- Double A Solar SLFSolar + storage · 133 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem