United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTTierra Bonita Solar
Tierra Bonita Solar is a 307 MW solar request built and operating in the ERCOT interconnection queue, in Pecos County, Texas.
Request details
- Queue ID
- 21INR0424
- Grid region
- ERCOT (Texas)
- Developer
- Greasewood II LLC
- Connection point (POI)
- 844 Nevilesw – 134905 Greaswod 345 kV
- Location
- Pecos County, Texas
- Technology
- Solar: 307 MW
- Total requested
- 307 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 14 October 2019
- Agreement signed
- 8 September 2022
- Proposed online date
- December 2024
- Came online
- December 2024
Location
Marker shows the centre of Pecos County; the queue data does not give exact sites.
Other requests in Pecos County
- Laurel Wind Energy CenterOnshore wind · 307 MW · agreement signed
- Longfellow Solar IISolar + storage · 207 MW · agreement signed
- Pecos Storage CenterWind + storage · 201 MW · agreement signed
- Longfellow Solar ISolar + storage · 178 MW · agreement signed
- Headcamp Energy Storage PlantBattery storage · 153 MW · agreement signed
- Longfellow BESS IISolar + storage · 106 MW · agreement signed
- Sherbino II BESS SLFBattery storage · 77.4 MW · agreement signed
- Longfellow BESS ISolar + storage · 55.0 MW · agreement signed
- Downtown BESSBattery storage · 10.0 MW · agreement signed
- Alamo Street BESSBattery storage · 10.0 MW · agreement signed
- Indian Mesa repowerOnshore wind · 9.3 MW · agreement signed
- Desert Sky repowerOnshore wind · 7.2 MW · agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem