United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTAjax Wind
Ajax Wind is a 367 MW onshore wind request built and operating in the ERCOT interconnection queue, in Wilbarger County, Texas.
Request details
- Queue ID
- 20INR0142
- Grid region
- ERCOT (Texas)
- Developer
- Lincoln Clean
- Connection point (POI)
- tap 345kV 6101 Riley - 1422 Bowman
- Location
- Wilbarger County, Texas
- Technology
- Wind: 367 MW
- Total requested
- 367 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 13 August 2018
- Agreement signed
- 14 July 2020
- Proposed online date
- December 2021
- Came online
- January 2022
Location
Marker shows the centre of Wilbarger County; the queue data does not give exact sites.
Other requests in Wilbarger County
- Felix North SolarSolar + storage · 201 MW · agreement signed
- Felix West SolarSolar + storage · 201 MW · agreement signed
- Felix East SolarSolar + storage · 201 MW · agreement signed
- Dundee West WindOnshore wind · 146 MW · agreement signed
- Blue Summit Energy StorageWind + storage · 100 MW · agreement signed
- Limitless Energy Hub IGas · 1,238 MW · in study
- Limitless Energy Hub IIGas · 1,238 MW · in study
- TexpoGas · 680 MW · in study
- Reunion SolarSolar + storage · 601 MW · in study
- Big Field SolarSolar · 506 MW · in study
- Poco Trail SolarSolar · 439 MW · in study
- Wander Waters BESSBattery storage · 304 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem