SOLAR Β· ERCOT

Jade Solar

Jade Solar is a 327 MW solar request built and operating in the ERCOT interconnection queue, in Scurry County, Texas.

Queue statusOperating
  1. PlanningQueued Jun 2020 (completed)
  2. ConsentedJan 2021 (completed)
  3. Construction (completed)
  4. OperatingJan 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0360
Grid region
ERCOT (Texas)
Developer
IP RENEWABLE ENERGY HOLDINGS LLC
Connection point (POI)
tap 345kV 11305 Dermott - 59904 Cottonwood
Location
Scurry County, Texas
Technology
Solar: 327 MW
Total requested
327 MW
Study phase
IA
Queue status
Operational
Entered queue
25 June 2020
Agreement signed
22 January 2021
Proposed online date
December 2023
Came online
January 2024

Location

Marker shows the centre of Scurry County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Scurry County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem