πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

ONSHORE WIND Β· ERCOT

Oveja Wind

Oveja Wind is a 300 MW onshore wind request built and operating in the ERCOT interconnection queue, in Irion County, Texas.

Queue statusOperating
  1. PlanningQueued Jul 2016 (completed)
  2. ConsentedJul 2018 (completed)
  3. Construction (completed)
  4. OperatingOct 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
18INR0033
Grid region
ERCOT (Texas)
Developer
Invenergy
Connection point (POI)
76005 Schneeman Draw 345kV
Location
Irion County, Texas
Technology
Wind: 300 MW
Total requested
300 MW
Study phase
IA
Queue status
Operational
Entered queue
11 July 2016
Agreement signed
24 July 2018
Proposed online date
September 2021
Came online
October 2021

Location

Marker shows the centre of Irion County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem