United States โบ Grid โบ Interconnection queues โบ Pennsylvania
OCTARY USA ยท INTERCONNECTION QUEUESSolar interconnection queue in Pennsylvania
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Mineral Basin Solar Power Solar ยท Mineral Basin Solar Power, LLC |
402 MW | In study |
| Solar project AI1-040, Elk County Solar |
250 MW | In study |
| Moonlight Flats Solar Solar ยท Moonlight Flats Solar Power, LLC |
250 MW | In study |
| Solar project AH2-397, Somerset County Solar |
200 MW | In study |
| Cornerstone Solar Solar ยท Cornerstone Solar, LLC |
200 MW | In study |
| Kimberlite Solar Solar ยท Kimberlite Solar Power, LLC |
175 MW | In study |
| Solar project AG2-176, Crawford County Solar ยท Trestle Solar Farm, LLC |
150 MW | In study |
| Ridgeway Solar Solar |
120 MW | Agreement signed |
| Shorebird Solar Solar |
117 MW | Paused / redesign |
| Hoodlebug Solar Energy Center Solar |
110 MW | Agreement signed |
| Bradford Solar Solar |
101 MW | Agreement signed |
| Solar project AI1-101, Lackawanna County Solar |
100 MW | In study |
| Rockdale Solar Solar |
100 MW | Agreement signed |
| Solar project AH2-405, Franklin County Solar |
100 MW | In study |
| Solar project AI1-038, Carbon County Solar |
95.8 MW | In study |
| Squab Solar Solar |
90.0 MW | Agreement signed |
| Solar project AH2-115, Tioga County Solar |
85.0 MW | In study |
| Solar project AH2-116, Cambria County Solar |
85.0 MW | In study |
| MPG Solar Solar |
83.6 MW | Agreement signed |
| Solar project AI2-063, Mckean County Solar |
82.5 MW | In study |
| Beaver Creek Solar Solar |
80.3 MW | Paused / redesign |
| Wilson Solar Solar |
80.0 MW | Agreement signed |
| Walker Solar Two Solar |
80.0 MW | Agreement signed |
| Swiftwater Solar Solar |
80.0 MW | Agreement signed |
| Solar project AH2-158, Somerset County Solar |
80.0 MW | In study |
| Strinestown Solar Project Solar |
79.6 MW | Paused / redesign |
| MPG Solar Solar |
78.4 MW | Agreement signed |
| Granite Hill Solar Solar |
70.0 MW | Paused / redesign |
| Solar project AI2-195, Lycoming County Solar |
69.9 MW | In study |
| Julius Solar Solar ยท Julius Energy, LLC |
66.0 MW | In study |
| Solar project AH2-195, Indiana County Solar |
65.0 MW | In study |
| Solar project AG2-411, Somerset County Solar ยท Iris Energy LLC |
63.0 MW | In study |
| Solar project AI1-105, Luzerne County Solar |
60.0 MW | In study |
| Mora Solar Solar |
60.0 MW | Agreement signed |
| Dover Solar Solar |
55.0 MW | Paused / redesign |
| Solar project AI2-196, Lycoming County Solar |
51.5 MW | In study |
| MC Solar I Solar |
50.0 MW | Agreement signed |
| Solar project AH2-135, Luzerne County Solar |
50.0 MW | In study |
| Maple Hill-Fiddlers 1 SP (Bear Rock) Solar ยท CPV Maple Hill Solar, LLC |
50.0 MW | In study |
| Solar project AF1-302, Jefferson County Solar |
42.0 MW | Agreement signed |
| Solar project AI2-475, Montour County Solar |
40.6 MW | In study |
| Poseidon Solar 1 Solar ยท Poseidon Energy, LLC |
40.0 MW | In study |
| Green Meadows Solar Solar |
40.0 MW | Agreement signed |
| Solar project AH2-295, Greene County Solar |
40.0 MW | In study |
| Solar project AG2-074, Carbon County Solar ยท Plainfield Solar, LLC |
38.0 MW | In study |
| Solar project AH2-129, Armstrong County Solar |
36.0 MW | In study |
| Cottontail Solar 7 Solar |
35.0 MW | Paused / redesign |
| Potter Solar Solar |
35.0 MW | Agreement signed |
| Solar project AI2-474, Montour County Solar |
34.8 MW | In study |
| Solar project AI2-471, Montour County Solar |
29.5 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)