SOLAR · PJMSolar project AG2-074, Carbon County
Solar project AG2-074, Carbon County is a 38.0 MW solar request in interconnection study in the PJM interconnection queue, in Carbon County, Pennsylvania, connecting to PPL.
- PlanningQueued Feb 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2023 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AG2-074
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PPL
- Developer
- Plainfield Solar, LLC
- Connection point (POI)
- Meckesville Tap 69kV
- Location
- Carbon County, Pennsylvania
- Technology
- Solar: 38.0 MW
- Total requested
- 38.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Active
- Entered queue
- 2 February 2025
- Proposed online date
- December 2023
Location
Marker shows the centre of Carbon County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Carbon County
- Mora SolarSolar · 60.0 MW · agreement signed
- Solar project AI1-038, Carbon CountySolar · 95.8 MW · in study
- PA Solar ParkSolar · 10.0 MW · built
- PA SPSolar · 10.0 MW · built
- Onshore wind project Z2-007, Carbon CountyOnshore wind · 213 MW · withdrawn
- Onshore wind project AA1-103, Carbon CountyOnshore wind · 209 MW · withdrawn
- Solar + storage project AH1-448, Carbon CountySolar + storage · 180 MW · withdrawn
- Onshore wind project N51, Carbon CountyOnshore wind · 101 MW · withdrawn
- Onshore wind project Z2-008, Carbon CountyOnshore wind · 99.0 MW · withdrawn
- Penn Forest Wind ProjectOnshore wind · 98.0 MW · withdrawn
- Broad MountainWind + storage · 90.0 MW · withdrawn
- Coal project V3-004, Carbon CountyCoal · 83.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem