United States β€Ί Grid β€Ί Interconnection queues β€Ί Pennsylvania

COAL Β· PJM

Coal project V3-004, Carbon County

Coal project V3-004, Carbon County is a 83.0 MW coal request withdrawn in the PJM interconnection queue, in Carbon County, Pennsylvania, connecting to PPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2009 (completed)
  2. Withdrawn / abandonedApr 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
V3-004
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PPL
Connection point (POI)
Siegfried
Location
Carbon County, Pennsylvania
Technology
Coal: 83.0 MW
Total requested
83.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study
Queue status
Withdrawn
Entered queue
6 August 2009
Proposed online date
October 2012
Withdrawn
April 2010

Location

Marker shows the centre of Carbon County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Carbon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem