πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Pennsylvania

ONSHORE WIND Β· PJM

Onshore wind project Z2-008, Carbon County

Onshore wind project Z2-008, Carbon County is a 99.0 MW onshore wind request withdrawn in the PJM interconnection queue, in Carbon County, Pennsylvania, connecting to PPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2013 (completed)
  2. Withdrawn / abandonedSep 2014 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Z2-008
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PPL
Connection point (POI)
East Palmerton-Wagner 69kV
Location
Carbon County, Pennsylvania
Technology
Wind: 99.0 MW
Total requested
99.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study
Queue status
Withdrawn
Entered queue
9 December 2013
Proposed online date
December 2017
Withdrawn
September 2014

Location

Marker shows the centre of Carbon County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Carbon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem