United States › Grid › Interconnection queues › Pennsylvania

SOLAR · PJM

Potter Solar

Potter Solar is a 35.0 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Potter County, Pennsylvania, connecting to APS.

Queue statusConsented
  1. PlanningQueued Feb 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AE2-074
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Potter 46 kV
Location
Potter County, Pennsylvania
Technology
Solar: 35.0 MW
Total requested
35.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Active
Entered queue
20 February 2019
Proposed online date
July 2026

Location

Marker shows the centre of Potter County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Potter County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem