Solar project AG2-463, Potter County

Solar project AG2-463, Potter County is a 80.0 MW solar request withdrawn in the PJM interconnection queue, in Potter County, Pennsylvania, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2021 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-463
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Gold β€šΓ„Γ¬ Tennessee Gas 115 kV II
Location
Potter County, Pennsylvania
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
30 March 2021
Proposed online date
October 2025
Withdrawn
December 2024

Location

Marker shows the centre of Potter County; the queue data does not give exact sites.