United States › Grid › Interconnection queues › Pennsylvania
SOLAR · PJMSolar project AH2-129, Armstrong County
Solar project AH2-129, Armstrong County is a 36.0 MW solar request in interconnection study in the PJM interconnection queue, in Armstrong County, Pennsylvania, connecting to APS.
- PlanningQueued Mar 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AH2-129
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Connection point (POI)
- Piney - Timblin 115 kV
- Location
- Armstrong County, Pennsylvania
- Technology
- Solar: 36.0 MW
- Total requested
- 36.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 1 March 2022
- Proposed online date
- May 2026
Location
Marker shows the centre of Armstrong County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Armstrong County
- McVille SolarSolar · 19.9 MW · in study
- Solar project AI1-143, Armstrong CountySolar · 19.9 MW · in study
- Solar project AH2-163, Armstrong CountySolar · 19.8 MW · in study
- South Bend CT1 - CT4Gas · 600 MW · built
- South Bend CT1 - CT4Gas · 104 MW · built
- South Bend Generating StationGas · 68.1 MW · built
- South Bend Generating StationGas · 10.0 MW · built
- South Bend Generating StationGas · 6.0 MW · built
- Mahoning Creek Dam Hydro ProjectHydro · 6.0 MW · built
- Gas project AC2-118, Armstrong CountyGas · 1,200 MW · withdrawn
- Gas project F05, Armstrong CountyGas · 646 MW · withdrawn
- Gas project B10, Armstrong CountyGas · 600 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem