HYDRO · PJMMahoning Creek Dam Hydro Project
Mahoning Creek Dam Hydro Project is a 6.0 MW hydro request built and operating in the PJM interconnection queue, in Armstrong County, Pennsylvania, connecting to APS.
Request details
- Queue ID
- T155
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Connection point (POI)
- Belknap 25kV
- Location
- Armstrong County, Pennsylvania
- Technology
- Hydro: 6.0 MW
- Total requested
- 6.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Operational
- Entered queue
- 29 January 2008
- Proposed online date
- March 2014
- Came online
- December 2013
Location
Marker shows the centre of Armstrong County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Armstrong County
- Solar project AH2-129, Armstrong CountySolar · 36.0 MW · in study
- McVille SolarSolar · 19.9 MW · in study
- Solar project AI1-143, Armstrong CountySolar · 19.9 MW · in study
- Solar project AH2-163, Armstrong CountySolar · 19.8 MW · in study
- South Bend CT1 - CT4Gas · 600 MW · built
- South Bend CT1 - CT4Gas · 104 MW · built
- South Bend Generating StationGas · 68.1 MW · built
- South Bend Generating StationGas · 10.0 MW · built
- South Bend Generating StationGas · 6.0 MW · built
- Gas project AC2-118, Armstrong CountyGas · 1,200 MW · withdrawn
- Gas project F05, Armstrong CountyGas · 646 MW · withdrawn
- Gas project B10, Armstrong CountyGas · 600 MW · withdrawn