🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Pennsylvania

GAS · PJM

South Bend CT1 - CT4

South Bend CT1 - CT4 is a 600 MW gas request built and operating in the PJM interconnection queue, in Armstrong County, Pennsylvania, connecting to APS.

Queue statusOperating
  1. PlanningQueued Jan 1999 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingMar 2002 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
B12_W01
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
South Bend 500 kV
Location
Armstrong County, Pennsylvania
Technology
Gas: 600 MW
Total requested
600 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study
Queue status
Operational
Entered queue
1 January 1999
Proposed online date
March 2002
Came online
March 2002

Location

Marker shows the centre of Armstrong County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Armstrong County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem