United States βΊ Grid βΊ Interconnection queues βΊ Ohio
OCTARY USA Β· INTERCONNECTION QUEUESBattery storage interconnection queue in Ohio
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Battery storage project AI1-167, Clermont County Battery storage |
250 MW | In study |
| Flint Grid Battery storage |
200 MW | Agreement signed |
| Battery storage project AG2-329, Wyandot County Battery storage Β· Wombat Solar LLC |
200 MW | In study |
| Battery storage project AH2-228, Pickaway County Battery storage |
150 MW | In study |
| Butterfly Meadows Battery storage Β· Butterfly Meadows Solar Project, LLC |
100 MW | In study |
| Battery storage project AH2-126, Jefferson County Battery storage |
100 MW | In study |
| Battery storage project AH2-217, Morrow County Battery storage |
100 MW | In study |
| Prairie Flyer Energy Storage Battery storage |
85.0 MW | Agreement signed |
| Battery storage project AH2-374, Richland County Battery storage |
84.0 MW | In study |
| Battery storage project AG2-289, Seneca County Battery storage Β· Chinchilla Solar LLC |
66.6 MW | In study |
| Hardin Energy Center βΓΓ¬ Storage II Battery storage |
55.0 MW | Paused / redesign |
| Clermont County Solar Project Battery storage |
52.2 MW | Paused / redesign |
| Timber Road Storage III Battery storage |
50.0 MW | Agreement signed |
| Hardin Energy Center βΓΓ¬ Storage I Battery storage |
50.0 MW | Paused / redesign |
| Cadence Energy Storage Battery storage |
50.0 MW | Paused / redesign |
| Paulding Storage II Battery storage Β· Paulding Wind Farm II LLC |
50.0 MW | In study |
| Vinton Energy Storage Battery storage |
42.0 MW | Paused / redesign |
| Hillclimber Solar Battery storage |
40.0 MW | Agreement signed |
| Battery storage project AG2-290, Seneca County Battery storage Β· Chinchilla Solar LLC |
38.4 MW | In study |
| Battery storage project AI2-483, Licking County Battery storage |
13.4 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)