United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Missouri (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown366,121 MW
Active in queue2,733 MW13 requests
Agreement signed535 MW2 requests
Withdrawn366,121 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

36 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project J3106, Pemiscot County
Solar + storage
500 MWWithdrawn / abandoned Pemiscot, MOMISO Sep 2022target 2025
Solar + storage project J3102, Pemiscot County
Solar + storage
500 MWWithdrawn / abandoned Pemiscot, MOMISO Sep 2022target 2025
Gas project GI-99, Butler County
Gas
470 MWWithdrawn / abandoned Butler, MOSoutheast Jul 2022target 2026
Solar project GI-97, New Madrid County
Solar
350 MWWithdrawn / abandoned New Madrid, MOSoutheast Jan 2022target 2024
Solar project GI-106, New Madrid County
Solar
350 MWWithdrawn / abandoned New Madrid, MOSoutheast Aug 2022target 2024
Solar project J2043, Callaway County
Solar
300 MWWithdrawn / abandoned Callaway, MOMISO Apr 2022target 2025
Solar project GI-98, New Madrid County
Solar
250 MWWithdrawn / abandoned New Madrid, MOSoutheast Jan 2022target 2024
Battery storage project J2198, Jefferson County
Battery storage
250 MWWithdrawn / abandoned Jefferson, MOMISO Mar 2022target 2024
Solar project GI-107, New Madrid County
Solar
250 MWWithdrawn / abandoned New Madrid, MOSoutheast Aug 2022target 2024
Solar project J2726, Montgomery County
Solar
248 MWWithdrawn / abandoned Montgomery, MOMISO Sep 2022target 2027
Onshore wind project J2915, Clark County
Onshore wind
223 MWWithdrawn / abandoned Clark, MOMISO Sep 2022target 2028
Solar project GEN-2022-079, Cedar County
Solar
192 MWWithdrawn / abandoned Cedar, MOSPP Sep 2022target 2027
Solar project J2425, Montgomery County
Solar
150 MWWithdrawn / abandoned Montgomery, MOMISO Sep 2022target 2027
Onshore wind project GI-111, Douglas County
Onshore wind
150 MWWithdrawn / abandoned Douglas, MOSoutheast Nov 2022target 2026
Solar project J1965, Callaway County
Solar
150 MWWithdrawn / abandoned Callaway, MOMISO Mar 2022target 2025
Battery storage project J2438, Montgomery County
Battery storage
150 MWWithdrawn / abandoned Montgomery, MOMISO Sep 2022target 2027
Solar project J2680, Dunklin County
Solar
150 MWWithdrawn / abandoned Dunklin, MOMISO Sep 2022target 2026
Solar project GEN-2022-053, Barton County
Solar
138 MWWithdrawn / abandoned Barton, MOSPP Jun 20222025
Solar project J3202, Iron County
Solar
120 MWWithdrawn / abandoned Iron, MOMISO Sep 2022target 2026
Battery storage project J2337, St. Francois County
Battery storage
100 MWWithdrawn / abandoned St. Francois, MOMISO Sep 2022target 2026
Battery storage project GEN-2022-031, Jackson County
Battery storage
100 MWWithdrawn / abandoned Jackson, MOSPP Jun 2022target 2026
Battery storage project J2506, Boone County
Battery storage
100 MWWithdrawn / abandoned Boone, MOMISO Sep 2022target 2026
Battery storage project J1986, St. Charles County
Battery storage
100 MWWithdrawn / abandoned St. Charles, MOMISO Mar 2022target 2025
Battery storage project J2584, Warren County
Battery storage
100 MWWithdrawn / abandoned Warren, MOMISO Sep 2022target 2026
Solar + storage project J2625, Marion County
Solar + storage
100 MWWithdrawn / abandoned Marion, MOMISO Sep 2022target 2026
Battery storage project GEN-2022-080, Cedar County
Battery storage
96.0 MWWithdrawn / abandoned Cedar, MOSPP Sep 2022target 2027
Other project GEN-2021-GR1, Jackson County
Other
88.0 MWWithdrawn / abandoned Jackson, MOSPP Mar 20222024
Battery storage project J2549, Clark County
Battery storage
75.0 MWWithdrawn / abandoned Clark, MOMISO Sep 2022target 2027
Solar project J3085, Madison County
Solar
75.0 MWWithdrawn / abandoned Madison, MOMISO Sep 2022target 2025
Battery storage project J2008, Callaway County
Battery storage
65.0 MWWithdrawn / abandoned Callaway, MOMISO Mar 2022target 2025
Solar project J3190, Audrain County
Solar
50.0 MWWithdrawn / abandoned Audrain, MOMISO Sep 2022target 2023
Solar project J2718, New Madrid County
Solar
50.0 MWWithdrawn / abandoned New Madrid, MOMISO Sep 2022target 2025
Solar project J2387, Stoddard County
Solar
50.0 MWWithdrawn / abandoned Stoddard, MOMISO Sep 2022target 2025
Gas project GI-100, Butler County
Gas
40.0 MWWithdrawn / abandoned Butler, MOSoutheast Jul 2022target 2026
Solar project J2981, Audrain County
Solar
30.0 MWWithdrawn / abandoned Audrain, MOMISO Sep 2022target 2023
Solar project GEN-2022-084, Jasper County
Solar
11.5 MWWithdrawn / abandoned Jasper, MOSPP Oct 2022target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)