Battery storage project J2198, Jefferson County

Battery storage project J2198, Jefferson County is a 250 MW battery storage request withdrawn in the MISO interconnection queue, in Jefferson County, Missouri, connecting to AMEREN MISSOURI.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2022 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2198
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN MISSOURI
Connection point (POI)
Joachim 138kV
Location
Jefferson County, Missouri
Technology
Battery: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
25 March 2022
Proposed online date
September 2024
Withdrawn
December 2025

Location

Marker shows the centre of Jefferson County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem